Frost │ │ │ │
prevention│ 2.0 │ │ │
Forms │ 12.5 │ 8.0 │ 6.1 │ =9.3=
Engineering │ 8.0 │ │ │
Length of day,│ │ │ │
hours │ 8 │ 10 │ │
Year of │ │ │
construction│ 1908 │ 1906 │ Pre-war conditions
──────────────┴─────────┴────────┴─────────────────────────────────────
Above a point 2 feet above the top of the sewer the method pursued and
the care observed in backfilling will depend on the character of the
backfilling material and the location of the sewer. If the sewer is in a
paved street the backfill is spread in layers 6 inches thick and tamped
with rammers weighing about 40 pounds with a surface of about 30 square
inches. One man tamping for each man shoveling is frequently specified.
If no pavement is to be laid but it is required that the finished
surface shall be smooth, slightly less care need be taken and only one
man tamping is specified for each two men shoveling. On paved streets a
reinforced concrete slab with a bearing of at least 12 inches on the
undisturbed sides of the trench may be designed to support the pavement
and its loads. This is of great help in preventing the unsightly
appearance and roughness due to an improperly backfilled trench. On
unpaved streets the backfill is crowned over the trench to a depth of
about 6 inches and then rolled smooth by a road roller. In open fields,
in side ditches, or in locations where obstruction to traffic or
unsightliness need not be considered, after the first 2 feet of backfill
have been placed with proper care, the remainder is scraped or thrown
into the trench by hand or machine, care being taken not to drop the
material so far as to disturb the sewer.
If the top of the sewer, manhole, or other structure comes close to or
above the surface of the ground, an earth embankment should be built at
least 3 feet thick over and around the structure. The embankment should
have side slopes of at least 1½ on 1 and should be tamped to a smooth
and even finish.
If sheeting is to be withdrawn from the trench it should be withdrawn
immediately ahead of the backfilling, and in trenches subject to caving
it may be pulled as the backfilling rises.
Puddling is a process of backfilling in which the trench is filled with
water before the filling material is thrown in. It avoids the necessity
for tamping and can be used satisfactorily with materials that will
drain well and will not shrink on drying. Sand and gravel are suitable
materials for puddling, heavy clay is unsatisfactory. Puddling should
not be resorted to before the first 2 feet of backfill has been
carefully placed. More compact work can be obtained by tamping than with
puddling.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account