It was decided to carry an aeroplane or seaplane to assist in aerial
observations and to be used as the “eyes” of the expedition in the
South. Flying machines had never before been used in Polar exploration,
and there were obvious difficulties in the way of extreme cold and lack
of adequate accommodation, but after consultation with the Air Ministry
it was thought possible to overcome them. The machine ultimately
selected was a “Baby” seaplane, designed and manufactured by the Avro
Company.
One of the first things done by Sir Ernest Shackleton in preparing for
the northern expedition had been the purchase of a small wooden vessel
of 125 tons, named the _Foca I_. She was built in Norway, fitted with
auxiliary steam-engines of compound type and 125 horse-power. She was
originally designed for sealing in Arctic waters, the hull was strongly
made, and the timbers were supported by wooden beams with natural bends
of enormous strength. The bow was of solid oak sheathed with steel. Her
length was 111 feet, beam 23 feet, and her sides were 2 feet thick. Her
draught was 9 feet forward and 14 feet aft. She was ketch-rigged, and
was reputed to be able to steam at seven knots in still water and to do
the same with sail only in favourable winds.
At the happy suggestion of Lady Shackleton she was re-named the _Quest_.
Sir Ernest received what he considered the greatest honour of his
life. The _Quest_ as his yacht was elected to the Royal Yacht Squadron.
Perhaps a more ugly, businesslike little “yacht” never flew the burgee,
and her appearance must have contrasted strangely with the beautiful
and shapely lines of her more aristocratic sisters.
She was brought to Southampton in March, 1921, and placed in the
shipyards for extensive alterations. The work was greatly impeded by
the strike of ship workers, the general coal strike which occurred at
that time, and by difficulties generally with labour, which was then
passing through a very critical period.
It had been intended to take out the steam-engines and substitute
an internal combustion motor of the Diesel type, but owing to the
difficulties mentioned this had to be abandoned, and on the advice
of the surveying engineer in charge of the work the old engines
were retained. The bunker space was readjusted at the expense of the
fore-hold, allowing a carrying capacity of 120 tons of coal, and giving
a steaming radius which, with economy and use of sail, was estimated at
from four to five thousand miles.
This work was in process when it became necessary to alter the plans
of the expedition, and Sir Ernest realized that the _Quest_, which had
been considered eminently suitable for the northern scheme, was not so
well adapted for the long cruise in southern waters. It was impossible
at this stage to change the ship, but further alterations were made on
deck and in the rigging generally to adapt her for the new conditions.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account