2. The Beech Wood Tunnel (situated about five miles north of
Coventry, and about 300 yards in length) was entirely relined with
bricks. Two hundred workmen were employed in this troublesome
operation for about six weeks without a single accident, and without
stopping the public, who, indeed, probably, during the whole period
of the repair, passed through without being even aware of the
execution of the job.
3. Between June, 1845, and October, 1848, the Company’s engineer
of the Southern District relaid 57 miles of single line of railway
without stopping a train and without accident.
At the Agricultural Meeting at Northampton in July, 1847, upwards of
11,000 persons were sent to Northampton, and 13,000 returned in the
evening, the carriages they occupied forming one mass as far as the
eye could reach. From the Company’s returns it appears that, of the
above number, not a single person received any injury; and although,
from some unaccountable reason, a good many of them on their return
walked, it is whispered, zigzaggedly, only two out of the whole
number were despatched to wrong destinations.
As the above facts require no comment, it is merely necessary to
explain by what description of arrangements the works of a great
railway can be repaired and renewed without stopping the public.
The two following specimens of the directions issued on such
occasions by the Company’s superintendent will best give the
information required:--
LONDON AND NORTH-WESTERN RAILWAY.
_Superintendent’s Office, Euston Station,
22nd January, 1848._
RELAYING THE RAILS IN THE KILSBY TUNNEL.
The Engineer Department have given notice that the workmen are
ready to commence removing the stone blocks and relaying the
rails in the Kilsby Tunnel.
The Electric Telegraph having been laid through the Tunnel,
the work is to commence on the night of Wednesday the 2nd of
February, and during its continuance the traffic is to be
conveyed over one Line from the passing of the Up Lancashire
Express Train (say 9 P.M.) until 8 o’clock the following
morning, when the Up Line is to be clear for the passage of
the 7 A.M. Train from Birmingham.
The passage of the Trains through the Tunnel during the
night is to be under the following regulations:--
The _Red_ Signal is to be kept on at each entrance to the
Tunnel during the hours the traffic has to pass over the
same Line; and every Train, whether Up or Down, is to stop
short of the Cross Road laid down at the Tunnel mouth.
As a guide to the Drivers where to stop, a Post has been
erected, upon which a Red Light will be shown, and beyond
which the Engine is not to advance.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account