The House Committee struck out these amendments and substituted a more
sweeping one than any yet suggested in the history of the road. This
amendment provided that a railroad be constructed west of Columbus with
the money appropriated for a highway. The committee reported, that,
after long study of the question, many reasons appeared why the change
should be made. It was stated to the committee by respectable authority,
that much of the stone for the masonry and covering for the road east of
Columbus had to be transported for considerable distances over bad roads
across the adjacent country at very great expense, and that, in its
continuance westward through Ohio, this source of expense would be
greatly augmented. Nevertheless the compact at the time of the admission
of the western states supposed the western termination of the road
should be the Mississippi. The estimated expense of the road's extension
to Vandalia, Illinois, sixty-five miles east of the Mississippi,
amounted to $4,732,622.83, making the total expense of the entire road
amount to about ten millions. The committee said it would have been
unfaithful to the trust reposed in it, if it had not bestowed much
attention upon this matter, and it did not hesitate to ground on a
recent report of the Secretary of War, this very important change of the
plan of the road. This report of the War Department showed that the
distance between Columbus and Vandalia was three hundred and thirty-four
miles and the estimated cost of completing the road that far would be
$4,732,622.83, of which $1,120,320.01 had been expended and
$3,547,894.83 remained to be expended in order to finish the road to
that extent according to plans then in operation; that after its
completion it would require an annual expenditure on the three hundred
and thirty-four miles of $392,809.71 to keep it in repair, the engineers
computing the annual cost of repairs of the portion of the road between
Wheeling and Columbus (one hundred and twenty-seven miles) at
$99,430.30.
On the other hand the estimated cost of a railway from Columbus to
Vandalia on the route of the Cumberland Road was $4,280,540.37, and the
cost of preservation and repair of such a road, $173,718.25. Thus the
computed cost of the railway exceeded that of the turnpike but about
twenty per cent, while the annual expense of repairing the former would
fall short more than fifty-six per cent. In addition to the advantage of
reduced cost was that of less time consumed in transportation; for,
assuming as the committee did a rate of speed of fifteen miles per hour
(which was five miles per hour less than the then customary speed of
railway traveling in England on the Liverpool and Manchester Railroad,
and about the ordinary rate of speed of the American locomotives), it
would require only twenty-three hours for news from Baltimore to reach
Columbus, forty-two hours to Indianapolis, fifty-four to Vandalia, and
fifty-eight to St. Louis.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account