In selecting a site, when the lay of the land will permit, place the
length of the house north and south, and arrange the incline and runs
with as few turns as practicable. The ice cakes require assistance
to keep them in motion on a crooked runway, and are constantly being
jammed and spalled. On a direct run of proper pitch the cakes will
travel without attention in freezing weather. On warm, sloppy days,
when the ice is soft, it will require assistance. The platforms for
winter shipments _via_ rail come in for attention in placing the
incline, which should be conveniently disposed for supplying them with
ice cakes as fast as they can be handled. System and dispatch are the
watchwords of the ice dealer while ice cutting is on.
SURVEY AND FOUNDATION.--The location and size of the house being
determined, a survey is made and all lines staked out. It is important
to have the foundations square and of the exact size, so that dimension
lumber and roof trusses will fit as designed. Levels, also, call for
attention, and the entire site should be brought to grade.
In the construction of foundations practice varies. They are partly
dependent upon local conditions and climatic influences. For large
houses, where the wastage is readily drained off and the sills are
comparatively dry, they are about as durable as the balance of the
building when placed directly on the ground.
The life of an ice house varies from so many causes, that no limit can
be given applicable to all cases. When the lumber is well selected and
the construction thorough, fifteen years of constant service will tell
plainly on the building. If repairs are made as often as required, its
term of usefulness is extended.
In warm climates, also for smaller houses, and for city supply depots,
foundations of stone or brick are employed to advantage. They should
be put in below frost, and extend about two feet above the surface.
[Illustration: FIG. 48. PLATE _A_. GROUND PLAN.]
DETAILS OF CONSTRUCTION.--In the building illustrated in plates _A_,
_B_, the sills are placed upon the ground. The house is divided into
four rooms, each forty feet wide in the clear, two hundred and fifty
feet deep, and forty feet high from sill to plate. The dimensions of
lumber required may be:
For outside sills, 8 × 10 inches, of such lengths as can most readily
be obtained.
Inside sills, 6 × 10.
Outside posts, 4 × 10 inches × 40 feet, set 12 feet apart.
Studding, 3 × 10 inches × 40 feet, with three feet centers.
Inside posts, 4 × 8 inches × 40 feet. Studding, 3 × 8 inches × 40 feet.
For outer circulating air space, the studding should be 2 × 8 inches ×
40 feet, with three feet centers.
For inner dead air spaces, 2 × 6 inches × 40 feet studding are placed
upright 12 feet apart, and horizontal cross studs 2 × 6 inches × 12
feet and three feet apart, are filled in between. This makes spaces 3 ×
12 feet on the inside of all the outer walls.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account