CANAL OF COMMUNICATION.—The quantity of earth-work to be
performed for the canal of communication and irrigation
is calculated from the sections at 10,320,884 _met. cub._
from the receipt of water to Lake Timsah. For this work
men will easily be found, at the rate of 3 _piast._ (0
_fr._ .75) including all expenses, and each workman will
do easily 2 _met._ _per diem_, which reduces the price of
the cubic _metre_ to 0 _fr_. 37½.
The cost of excavating the canal will therefore be 3,870,331
For the small canal of irrigation, leading from the last
channel to Suez, the quantity of earth-work is 2,218,500
_met. cub._ For this it will be necessary to pay the men
0 _fr._ 90 _per diem_, and they will easily do 2 _met._
25 _cub._, which will be 0 _fr._ 40 per _met. cub._
The cost of this part will therefore be 887,400
Add 10 _per cent._ for tools 6,529,667
Contingencies 173,654
----------------
Total for the first part _fr._ 72,000,000
ARTICLE II.
WORKS OF ART.
To give a concise but accurate notion of the expense of the works of art,
we shall fix the prime cost of the materials, compared with the prices
paid in the execution of the works of the barrage, and then it will be
easy to determine the outlay necessary for the present works, as compared
with that of the former.
ROUGH STONE.—The rough stone used in the barrage comes
from the quarries of Toura, situated 30 _kil._ from
the place where it is used. It costs 22 _paras_ the
_quintal_, or 4 _fr._, 20, the _cubic metre_, delivered
on the spot. That which will be used in the works of the
Maritime Canal will come from the quarries of Ataka, on
the shores of the bay of Suez, at a distance of 20 _kil._
from Suez. This being a calcareous stone, like that of
Toura, if it is brought to the boats by a railroad and
towed by steamers, there is sure to be a saving in the
extraction and transport. We have however, taken the
price at 5 _fr._ to cover all difficulties in forming
establishments, the higher rate of labour, and the cost
of the railroad. This is the price paid for the blocks
employed at the port of Cherbourg.
At the port of Valencia (in Spain), the extraction of
large blocks, the transport to the quay and loading, only
cost 4 _fr._ 25.
HEWN STONE.—The hewn stone for the barrage, came from
the quarries of Toura and Massara, at an average distance
of 33 _kil._ from the place where used. These stones were
first transported a distance of 6 _kil._ to the banks of
the Nile, by means of bullock carts, then transferred
to sailing barges, and carried by water to the distance
above-mentioned.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account