Since the beginning of last week, however, four trains per day have
been run regularly, stopping at the stations, and keeping their
time as if working for traffic. The tube and valve appear in good
order, and the whole has worked well, but the running in this
manner can alone show the deficiencies which may still exist in the
details necessary for stopping, and starting quickly from the
stations, and all the other minor operations incidental to working
the traffic in the ordinary course; and, until all these
arrangements are completed, and the engines in more perfect order,
I think it would be much better to defer at least the substitution
of the Atmospheric for the locomotive working. Trains, in addition
to those now running may perhaps be advantageously worked for the
public, after a further short continuance of the present
practising.
The two engines completing the number to Newton are nearly ready
for trial, and it is to be presumed that, after the experience of
the past, the makers will be enabled to put them at once into an
efficient state.
The delays and difficulties attending the bringing into operation
the Atmospheric System upon this portion of the railway have been
beyond all anticipation, and beyond what any previous experience
would have justified anybody in anticipating. The difficulties have
all been seriously aggravated by the necessity (consequent,
certainly, upon the original delays) of working the line with
locomotives during the construction and completion of the
Atmospheric apparatus. Not only has the constant occupation of the
line interfered with the progress of the work, but it has been
necessary to devise all the arrangements so as to admit stations,
sidings, and line being worked either by locomotive or by
Atmospheric in succession, or even at the same time.
These difficulties, added to those always consequent upon the
introduction of any new system, have been most wearying and
incessant, and I am not surprised that the public and the
proprietors should have been impatient. I trust the ultimate result
will remove any grounds for disappointment.
The stress of personal anxiety and personal fatigue, experienced by Mr.
Brunel and by all who were engaged in the work, was very severe, and
continued so to the end. Not only was the progress in the completion of
the work slow, but in spite of every exertion the results were
incessantly marred by unfortunate contingencies which involved further
delay, discouragement, and expenditure. Moreover, the reaction which
followed the railway mania had set in; calls were ill responded to, and
great difficulty was experienced in raising the money requisite for the
completion of the line.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account