The floors of the Miraflores and Pedro Miguel locks will have 1 foot
thickness of concrete on top of the rock as a wearing surface. At
Gatun, however the rock is of a character susceptible to the weather.
It has therefore been considered necessary, in constructing the floor
here, to leave the rock above grade until just before the concrete is
to be placed and then to scrape and wash the surface to be covered. The
floor in the lower portion of the upper chamber is to be of concrete
3 feet thick. The rock here is considered thick enough to withstand
the pressure from the water-bearing stratum below. Above the middle
gate, however, this stratum is too thin, and a floor 13 feet thick of
concrete is provided and anchored by rails set in holes and surrounded
by concrete.
The main floor level will be about 2 feet below the sills, in order
that small objects dropped from vessels may be passed without being
struck.
The sills for the gates are designed as concrete arches in a horizontal
plane, 31 feet thick throughout and of 100 feet radius at the extrados.
The filling system is designed so that, with all valves opened the
chamber can be filled in 8 minutes, but to prevent possible damage to
vessels in the lock the maximum rate will probably not be allowed to
exceed 3 feet a minute which would correspond to less than 15 minutes
for filling.
Most of the foregoing discussion is taken from the Engineering Record
of February 26, 1910.
There has been much criticism of the lock sites, but the engineers now
in charge seem to have perfect confidence in their work.
During the fiscal year 1908–’09 the work of excavating for the Gatun
locks was continued by steam shovels and one 20-inch suction dredge.
Material excavated in the dry amounted to 933,546 cubic yards, and that
in the wet to 479,950 cubic yards. It was decided to construct curtain
walls to stop any underflow; these will extend across the lock under
the sill of the emergency dam and downstream outside the walls to the
intermediate gates. As an additional precaution to making the concrete
floor 13 feet thick as before mentioned a system of sumps under the
floor with telltales in the walls will be built.
The plant for the construction of the locks is practically installed
and ready for work, it being operated entirely by electricity.
At the Pedro Miguel locks 715,726 cubic yards were removed in 1908–’09.
One lock chamber was completed to grade, but 45,000 cubic yards remain
for removal in the other one.
At Miraflores work was done the past year with steam shovels and one
suction dredge. The total amount excavated was 1,147,527 cubic yards
which is one-half of the total estimated quantity.
IX. CONSTRUCTION OF THE DAMS
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account