The Spaniards had commenced harbour work at Manila in 1892,
twenty-five years after preliminary study began and sixteen years
after prospective plans had been submitted. Their operations were
stopped by the insurrection in 1896, at which time the present west
breakwater had been about half completed, but as the completed portion
was at the shore end and in shallow water it afforded no protection to
ships. There had been constructed twenty-four hundred feet of masonry
wall partly enclosing one of the basins provided for in the Spanish
plans, and fourteen hundred eighty-five feet of wall lining canals
connecting the proposed new harbour with the Pasig River. These also
were temporarily useless, because there had been no dredging in front
of them, or backfilling in their rear.
Outside of Manila practically nothing had been done to facilitate the
loading and discharge of vessels, or to protect them from the elements.
We now have at Manila a deep-water harbour dredged to a uniform depth
of thirty feet and enclosed by two breakwaters having a total length
of nearly eleven thousand five hundred feet. Two hundred and sixty-one
acres of land have been reclaimed with the dredged material. Two steel
piers extend from the filled land into the deep-water harbour. One of
these is six hundred fifty feet long and one hundred ten feet wide,
the other six hundred feet long and seventy feet wide. Both are housed
in, the sheds covering them having a total area of ninety-two thousand
square feet. These piers and sheds are practically fireproof, and
the largest ocean-going steamers on the Pacific can lie alongside
them. Additional work planned, which should be undertaken when
funds permit, includes two more piers; and bulkheads to connect the
inner ends of the present piers, so as to give inter-island steamers
opportunity to unload.
At Cebú the sea-wall has been completed to a length of two thousand
sixty feet and the channel in front of it dredged in part to ten and a
half and in part to twenty-three feet at low water. Some ten and a half
acres of land have been reclaimed with the material removed. Streets
and roadways have been built on the reclaimed area, and a wharf eight
hundred twelve feet in length, designed as an extension to the wall,
is now fifty per cent completed. The harbour at Cebú should ultimately
be dredged so as to give thirty feet of water along the piers.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account