The total length of the work is 2,260 feet, and it is built up to 10
spans, each measuring 120 feet, and 7 spans of 60 feet apiece. The
girders forming the deck are supported on steel towers spaced 40 feet
apart. The height of the rails at the highest pier is 325 feet above
the floor of the gorge, and 825 feet above the Chungzoune stream. No
less than 232,868 separate pieces of steel had to be handled on the
site, and the natives had to drive 200,000 rivets to secure the fabric
together.
Owing to the remote point at which work was being carried out--10,000
miles by sea from home--an elaborate cable code was drawn up, each
integral part of the viaduct, as well as details of the erecting plant,
having a distinctive word. In addition, there were special words for
the purpose of reporting the progress of the erection to headquarters.
Every week the chief engineer cabled home a full progress report
at a cost of 5_s._, or $1.25, per word. The men were provided with
a well-equipped medicine chest, and a complete photographic outfit
constituted an important part of the organisation, photographs being
dispatched to Steelton regularly to supplement the cabled and written
report on the progress of the undertaking. Only one man was lost in the
enterprise, and this was attributable to fever produced from indulgence
in alcoholic liquor. No other fatality was recorded either among the
natives or Americans, and no serious accident marred the work, which,
bearing in mind its magnitude and character, was highly satisfactory.
The actual erection occupied nine months, work being continued
uninterruptedly through the wet season, when, fortunately, the
greater part of the annual 150 to 200 inches of rain fell during the
night. Although the viaduct is 24½ feet wide across the top, which is
sufficient to carry a double track, only one road is laid at present.
The bridge also enables pedestrians to cross from one side of the chasm
to the other, refuge platforms being provided at frequent intervals
to enable those afoot to escape being run down by passing trains. Upon
completion, the structure was subjected to severe tests spread over a
period of two months, and these proving satisfactory, the structure
was accepted by the railway authorities. The mammoth steel traveller
weighing 100 tons, and which had played such an important part in the
rapid erection of the viaduct, was demolished and sold for scrap.
By the provision of this viaduct at the selected height the track is
led to a natural ledge on the opposite cliff-face. While the viaduct
was under construction the railhead was pushed forward, the material
for the grade being transported across the valley by the overhead
cable. By the time trains were able to cross the structure, the end of
steel had reached a point some 35 miles beyond.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account