The firm who accepted the contract undertook to complete the work
for £158,400, or $792,000, which was considered to be a very low
price. It was attacked from both ends, and mechanical boring was
adopted. Convenient water power was harnessed to drive the Brandt rock
drills, which worked under a pressure of some 1,200 pounds per square
inch. Boring proceeded somewhat slowly, more so, in fact, than the
contractors had anticipated; but this was due to the extreme hardness
of the rock encountered, while the work was handicapped by delays which
the contractors could not have controlled. In the first place labour
proved scarce and expensive. The men working on the coast, although
experienced in drilling and blasting rock, could not be persuaded to
proceed up-country to practise their skill. The situation was too
remote, and the elements were too bitter, and seeing that extensive
railway construction was proceeding at the same time in other and more
congenial parts of the country, there was no cogent reason why the men
should hie to an inhospitable locality for work.
The tunnel-borers, however, were spared the tribulations which have
assailed their colleagues in other parts of Europe. Faults in the rock
strata were very few and far between, while subterranean streams and
pockets of viscous mud did not overwhelm them. The temperature within
the boring, moreover, never rose to an intolerable point, the maximum
recorded being 52° Fahrenheit. This was in striking contrast to the
conditions on the Gotthard, Cenis, Simplon, and other central European
tunnels, where the mercury rose at times to the vicinity of 90 degrees.
Yet the workers in the Gravehals tunnel experienced their own peculiar
dangers and exasperating misadventures. The climatic conditions were
the most trying, and many men abandoned their tasks after a short
experience in this bleak situation, for work at a lower level. This
monotony was varied one day by an avalanche, which crashed down the
mountain-side, smashed into the power-house and carried away some of
the machinery. Work had to be suspended for some six weeks while the
damage thus caused was repaired. At another time work could not be
carried forward because no water was available, and about two months
of enforced idleness had to be endured until the turbines could be set
going once more.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account