By the terms of the supplementary Charter of 1864, a great incentive
was given the two Companies, the Union Pacific Railroad and the
Central Pacific Railroad to get down as great a mileage as possible.
In addition to the Government grant of Land and Bonds based on
mileage, there was the traffic of the Mormon country and Salt Lake
City at stake. Besides this, it was readily seen that the line having
the greatest haul would be correspondingly benefitted when it came to
subdividing earnings on trans-continental business. With these for
incentive, both Companies put forth every effort to cover the ground.
In the early part of 1869, rails of each Company were going down from
six to ten miles a day. Records in track-laying were made then that
have never been broken. Near Promontory a sign is still standing to
announce "Ten miles of track laid in one day." Actual figures are not
obtainable, but reliable contemporaries at that time stated there were
twenty-five thousand men employed on the construction work of the two
lines, as well as six thousand teams and two hundred construction
trains. Both Companies were anxious to establish point of advantage
that they could use in the controversy that was inevitable and which
would determine the mileage and territory each was to enjoy. On April
29th, nine and a half miles remained unfinished. Three and a half for
the Central Pacific Railroad, they having laid ten miles the day
before, and six miles for the Union Pacific Railroad, the latter being
the ascent of Promontory Hill and including a stiff bit of rock work.
When the two tracks came together, the Central Pacific Railroad had
nearly sixty miles of grading done parallel to the Union Pacific
Railroad track--that is from Promontory east to the mouth of Weber
Canon, while the Union Pacific Railroad had located their line to the
California State line and most of the grading was done as far west as
Humboldt Wells, Nev., four hundred and fifty miles from Ogden.
As stated the two tracks were brought together at Promontory on May
9th, 1869, but two rail lengths were kept open until the questions at
issue were adjusted and also until a suitable program could be
arranged for celebrating the event. Everything satisfactorily
arranged, Monday, the 10th of May, 1869, was set for the ceremonies.
The Central Pacific Railroad completed their track up to Promontory
May 1st. It was the intention to have the opening ceremonies on
Saturday, May 8th, and the Central Pacific officials were on hand for
that purpose. The Union Pacific party coming west were delayed some
forty-eight hours at Piedmont by a gang of graders and track-layers,
who not having received their wages side tracked the special train
with Vice-President Durant and his party, holding them as hostages
until the Company had paid over to the contractor some two hundred and
fifty thousand dollars due him and which he in turn distributed among
his men.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account