The idea of cost of reproduction is not synonymous with the idea
of the cost of building a railway capable of serving the same
transportation purpose. If all our railways were to be built anew, in
the light of our present knowledge, and with our present traffic
offerings and financial resources, vast changes would be made in the
character of construction. The physical fact of existing construction
prevents a theoretical substitution of what is the best construction for
any community, together with its costs for the construction which was
actually made years ago.
In the event that an estimate of reproduction costs be made for a State
as a whole, or for a great railway system as a whole, the conception of
reproduction is modified so that the construction may take the form of
progressive construction, the principal lines being built first and the
less important lines afterward. This method will require the estimate
for interest during the construction period to be greater.
The money cost of the seasoning and the adaptation of the roadway to
such a condition as will permit heavy trains to be run at high speeds,
is great, but the amount is not readily ascertained. An estimate of cost
of reproduction, to be true, must consider this item; and probably the
more usual method of ascertaining it is to assume it to be an amount in
some proportion to the cost of the excavation. This proportion will vary
with the character of the material through which and of which the cuts
and fills are made, and with the methods of construction necessarily
adopted. There are many railways on which this cost will exceed 25% of
the total cost of excavation.
After the estimate has been made, including the item for seasoning and
adaptation, there should be added a contingent fund to cover the omitted
work, consisting of small borrow-pits and ditches, undetermined
foundations, unexpected conditions encountered, unavoidable "force
account" work, minor changes of streams and highways, damages to
adjoining lands due to the methods of construction and to diversion of
water, etc. This item will not exceed 5% of the cost of the roadway if
the estimate be accurately made.
The more convenient form into which an estimate of cost of reproduction
of a steam railway is to be put is to follow the sub-accounts, as
prescribed by the Interstate Commerce Commission for Expenditure for
Road. Each item given in that accounting has a place in the estimate.
These comments are confined to the items covering the roadway, namely,
Right of Way and Station Grounds, Grading, Tunneling, Bridges, Trestles,
and Culverts.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account