Three breaks only have been reported as due to defective metal or
casting. No break of a sound shell of full thickness has been found.
_Trenching_.--Deep frosts are unknown in this section. The pipe was laid
so that the top was about 1 ft. below the surface of the ground. The
trenching was a simple matter. Part of the work between Bonito and the
railway on the Carrizozo plain was done by Buckeye ditchers. All other
ditching was done by a railroad plow followed by pick and shovel, or by
the two latter tools only. The ditcher could open 2,000 ft. of trench per
day, but averaged about 500. The plow and 35 men could open 3,500 ft. A
chain about 6 ft. long separated the end of the plow beam and the double
tree. In this way the trench was plowed to the bottom. Two mules, two
men, and a scraper could back-fill 3,500 ft. per day.
_Pipe Laying_.--Between Bonito and the railway, one gang of ten men
could lay 4,000 ft. of 12-in. pipe per day. The average was much less,
owing to a variety of causes. At the end, the railway company added to
the contractor's force, and laid the last 10 miles of pipe in 7 days,
there being a half dozen separate gangs at work.
Along the railway, the day's record on wood pipe was 4,000 ft. of 11-in.,
6,200 ft. of 7-1/2-in. and 8345 ft. of 3-1/2-in, pipe laid by a gang of
eight men after the pipe was distributed along the trench. These eight
men, of whom five were Americans, laid 76 miles of pipe, and became
expert. Their operation was like the working of a clock.
On the 12-in. iron pipe, the regular day's work was 96 joints, or 1,152
ft. of pipe laid and caulked. The record was 1,644 ft. Two gangs laid
101,300 lin. ft. in 60 days. Such a gang consisted of 1 foreman, 1
inspector, 8 caulkers, 4 yarners, 1 melter, 1 pourer, 1 helper, and 10
men putting pipe into the trench.
_Cost Data_.--The pipe from Bonito to the railway was laid by contract.
The price was 18 cents per lin. ft. laid and back-filled from the
railway to the Nogal Reservoir, and 28 cents from Nogal to Bonito. In
addition, 50 cents per ton per mile was paid for hauling pipe, and extra
compensation for setting valves. From Coyote, east along the railway,
the work was done by the railway company under the writer's direction.
The total cost of laying 384,300 ft. of wood pipe, from 11 to 3-1/2 in.
in diameter, was $18,156.77, or 4.72 cents per ft., divided as follows:
Ditching $0.0249
Laying 0.0113
Back-filling 0.0110
-------
Total $0.0472
This includes unloading from the cars. Train service cost 1/3 cent per
ft. additional.
The pipe gang, including back-filling, consisted of 1 foreman, at $100
per month, one assistant foreman at $75, and about 30 Mexicans at $1 per
day. The rates were the same in the ditching gang. The plow team cost $6
per day.
Including all general expense, the cost does not exceed 6 cents per lin.
ft.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account