This was done by Oscar Lindstrom on a basis of cost plus ten per cent.
A half-viaduct seventy-five feet in length was built containing
fifty-three cubic yards of concrete and 4,100 pounds reinforcing steel,
with standard bridge railing for guard fence.
Two hundred and fourteen linear feet of rubble masonry walls were built
on a slope of three-fourths to one, and standard bridge railing placed
on top for guard fence. These walls contain 438 cubic yards of rock.
A reinforced concrete crib forty-one feet long, fifteen feet high and
seven feet wide was built and filled with large rock. The members were
cast on the dock in Rainier and hauled to the location. A reinforced
concrete slab on solid earth foundation was used for footing, on the
required angle to give the crib a batter of one-fourth to one.
The total cost of the Prescott Hill improvement was $9,039.86.
Goble Creek Bridge
A ninety-foot reinforced concrete bridge was built over Goble Creek on
the Columbia River Highway about one-half mile east of Goble. This
bridge has a pile foundation which was put in by the Warren Construction
Company on a cost plus basis for $1,583.32. The superstructure was built
by Lindstrom and Fiegeson on a unit price basis. The cost of the
structure complete was $5,907.14.
The engineering work in connection with this work was handled by H. C.
Compton, resident engineer, on the Goble Section, and the inspection of
the placement of steel and pouring of concrete was in charge of L. M.
Huggins.
COST STATEMENT--GOBLE CREEK BRIDGE
Engineering $ 77.47
Construction--
Class A concrete, 135 cu. yds. at $18.40 $2,447.20
Reinforcing steel, 17,925 lbs. at 7½c 1,344.38
Concrete hand rail, 186 lin. ft. at $1.75 325.50
Construction of cement shed and unloading cement 129.27
Pile foundation (force account) 1,583.32
---------
Total construction cost 5,829.67
---------
Grand total cost of bridge $5,907.14
Beaver Creek Bridges
For a considerable distance between Rainier and Clatskanie the Columbia
River Highway follows Beaver Creek, crossing the creek in many places.
To replace a number of temporary wooden structures and to provide
bridges at every crossing, the highway department in 1917 and 1918
constructed nine reinforced concrete bridges across this stream. The
spans of these structures vary from thirty to 105 feet, there being one
thirty-foot, one fifty-foot, two sixty-foot, four seventy-foot and one
105-foot spans in all.
The thirty-foot span structure was built by L. O. Herrold of Salem, on a
cost plus ten per cent basis and cost $3,600.00.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account