Third biennial report of the Oregon State Highway Commission : $b covering the period December 1st, 1916 to November 30th, 1918
Benson, Simon
Highway engineering -- Oregon -- History; Water resources development -- Systems engineering -- Oregon -- History
Engineering $ 468.38
Construction--
Common excavation, 1,925 cu. yds. at 30c $ 577.50
Intermediate excavation, 1,071.9 cu. yds. at
48c 514.51
Solid rock excavation, 1,039.7 cu. yds. at
$1.25 1,299.62
Overhaul per 100 lin. ft., 905 cu. yds. at 3c 27.15
12-inch corrugated iron pipe, 228 lin. ft. at
$1.00 228.00
Force account--
Excavation for cribbing and placing rip-rap 61.93
8-foot extension to 36-inch culvert 54.63
Widening old roadbed, removal of slides and
general improvement work not subject to
measurement 3,082.56
Culvert pipe furnished by State 36.33
---------
5,882.23
----------
Total cost $6,350.61
Beaver Valley Grading
Before the Columbia River Highway through Beaver Creek Canyon between
Delena and Inglis was opened for traffic in July, 1918, in order to
reach Clatskanie from Delena, it was necessary to travel over a narrow,
dangerous, earth and corduroy road, either by way of Maygar and Quincy
or through the hills about eight miles into Clatskanie. Both of these
roads were passable for autos only about three months during the dry
season.
The grading of this section was partly completed by the County under
supervision of Mr. Bowlby, State Highway Engineer in 1914. This section
being a very important link in the Columbia River Highway and no funds
being available from County or State funds during 1915 or 1916, S.
Benson decided to advance the necessary funds to make this section
passable. About four miles of grading was completed between Inglis and
Delena, leaving only the building of bridges to open this section. This
work was later macadamized by the State.
The engineering work was done by A. K. Grondahl.
A bill was passed by the 1917 Legislature refunding to Mr. Benson
$20,978.22 which is a large portion of the amount expended by him.
COST STATEMENT
Clearing and grubbing $ 1,265.80
Grading--labor and teams 17,124.07
Explosives 2,275.31
Pipe culverts 313.04
----------
Total $20,978.22
Prescott Hill Section
This section of the highway was built along the steep hillside, several
slides having occurred narrowing the roadbed in some places to about
eight feet and making it very dangerous, it was necessary to build
several retaining walls, half viaducts and guard fences.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account