In September and October, 1918, the State Highway Commission made a
location survey on the section of the Bend-Burns Highway between Rolyat,
in Deschutes County and the One Hundred Mile Road, in Harney County. The
object of the survey at this time is to secure a more direct route and
to avoid the bad section of the present road through the Glass Buttes
district. The length of this survey is seventeen and one-tenth miles and
it materially shortens the distance, as compared with the present road
between the terminal points mentioned.
Fifteen and six-tenths miles of this line are in Deschutes County and
one and five-tenths miles in Harney County. The northeast corner of Lake
County is touched by the survey but only for a short distance. The
definite limits are not shown as the County Lines could not be found and
it was deemed not advisable to go to the cost of reestablishing the
lines for the purpose of the survey. The new location leads in an
easterly direction from Rolyat and continues to the north of the present
road.
The plans for this survey will be made up in the near future. H. B.
Wright was the locating engineer in charge.
DOUGLAS COUNTY
As a result of the liberal co-operation of Douglas County, a very large
amount of work has been done during 1917 and 1918 on the Pacific Highway
across that County. From a $500,000.00 bond issue the County set aside
$200,000.00 for the improvement of the Pacific Highway north of
Roseburg, with the understanding that the Highway Department would
expend an equal amount on the same highway south of Roseburg. In
accordance with this arrangement, it was agreed that the County would
grade 10.4 miles between Yoncalla and Oakland, grade and macadamize 4.6
miles between Comstock and Leona, and grade 2.4 miles between Comstock
and the Lane County Line; and that the State would grade 12.8 miles
between Myrtle Creek and Dillard and macadamize 2.4 miles between
Comstock and the Lane County Line. It was further agreed that if the
County would cooperate with the State and Federal Government to the
amount of $23,000.00 on the Canyonville-Galesville Forest Road Project,
this amount would be considered a part of the $200,000.00 to be provided
by the County in connection with the general scheme of improvement
outlined.
All of the work contemplated in this co-operative agreement has been
carried to completion, and when final payments have been made the total
expenditure by the State will be approximately $205,000.00 and by the
County $175,000.00.
The Canyonville-Galesville Forest Road Project referred to above
involves the grading of a 9.7 mile section over Canyon Creek Pass, and
it will eliminate one of the very worst stretches on the Pacific Highway
between Portland and the California Line. This is estimated to cost
$211,000.00, of which the County will pay $23,000.00, the State
$94,000.00 and the Federal Government $94,000.00.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account