This section is through the south end of Pass Creek Canyon, beginning
approximately a mile and a half south of Comstock and extending to a
point a half mile north of Leona, being 4.6 miles in length. The
contract was a joint contract signed by the County Court and State
Highway Commission and was awarded to Hall & Soleim of Eugene on
September 5, 1917. Work covered by the contract was for grading and
macadamizing, culverts and bridges.
Due to shortage of labor, poor shipments on macadam rock, and financial
difficulties, the contractors were obliged to ask the State Highway
Commission to take over the work. On August 20, 1918, after a conference
with the County Court and the Contractor's Surety Company, this was
done. The work was completed November 30, 1918. The construction details
under the State supervision were handled by a State construction
engineer, representing the Contractors and Surety Company, and the
engineering details by the resident engineer on the work--the latter
rendering regular monthly estimates of work done on the unit contract
prices, of the original contract.
This work complete will cost approximately $80,000.00 of which the
County will pay $74,349.72 and the State $5,650.28.
The construction of this section was in charge of E. B. Bishop, resident
engineer, and F. E. LaPointe, construction superintendent.
Grading--Oakland to Yoncalla
This work extends from the Calapooya River Bridge at Oakland to a point
two miles south of Yoncalla, a total distance of 10.4 miles. A contract
for clearing, grading and culverts was awarded the Warren Construction
Company, September 5, 1917, being the last of three contracts signed
jointly by the County Court and State Highway Commission.
This work was completed July 25, 1918, and is an excellent piece of
standard construction 24 feet in width. It eliminates the old excessive
grade over Rice Hill, and some bad sections just north of Oakland--there
being now no grades over 5 per cent.
On the completion of the grading the State Highway Commission requested
permission Of the Capital Issues Committee to sell bonds, part of which
were to cover the rocking of this unit to make it passable for winter.
This request was refused on the ground that it was not a necessary war
measure. The road will therefore not be passable this winter, but it is
expected that the section will be macadamized during the 1919 season.
Mr. Robert A. Pratt was resident engineer in charge of the construction.
DETAILED EXPENDITURE STATEMENT--GRADING--OAKLAND TO YONCALLA
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account