Third biennial report of the Oregon State Highway Commission : $b covering the period December 1st, 1916 to November 30th, 1918
Benson, Simon
Highway engineering -- Oregon -- History; Water resources development -- Systems engineering -- Oregon -- History
Construction--
Clearing and grubbing $ 500.00
Common excavation, 10,231 cu. yds. at 60c 6,138.60
Intermediate excavation, 8,689.4 cu. yds.
at 80c 6,951.52
Solid rock excavation, 7,722.2 cu. yds.
at $1.25 9,652.75
12-inch reinforced concrete pipe, 391 lin. ft.
at $1.25 488.75
36-inch reinforced concrete pipe, 56 lin. ft.
at $4.00 224.00
6-inch porous drain tile, 585 lin. ft. at 10c 58.50
Class A concrete, 48 cu. yds. at $15.00 720.00
Class C concrete, 2 cu. yds. at $12.00 24.00
Rubble masonry, 2 cu. yds. at $1.25 2.50
Overhaul per 100 lin. ft., 54,862 cu. yds.
at 2c 1,097.24
Crushed rock for drain tile, 30 cu. yds. 46.20
18-inch concrete pipe in place, 45 lin. ft. 87.15
-----------
$ 25,991.21
Less 15 per cent retained pending completion 3,898.68
-----------
22,092.53
-----------
Total expended to November 30, 1918 $ 24,037.20
Paid by State--engineering 1,944.67
Paid by County--construction 22,092.53
-----------
Total $ 24,037.20
This work is estimated to cost complete $ 27,500.00
[Illustration: BITUMINOUS PAVEMENT ON THE PACIFIC HIGHWAY SOUTH OF
OREGON CITY IN CLACKAMAS COUNTY. GRADED AND PAVED IN 1918]
Paving--Oregon City to Canby
A contract was awarded on September 4, 1917, to the Oregon Hassam Paving
Company of Portland, for a sixteen-foot bituminous pavement between
Oregon City and Canby, a distance of 7.5 miles.
A considerable part of the crushed rock used in this pavement was
furnished by the Highway Department from a rock point which it was
necessary to remove in connection with the grading just north of New
Era.
The paving of this section is practically complete at this date and the
contracting company is to be complimented upon the excellence of its
work. The cost of the work completed will be about $135,000.00 of which
amount $102,114.85 has been paid.
Mr. M. E. DeWitt acted as resident engineer for the Highway Department
on this work.
DETAILED STATEMENT OF EXPENDITURES TO NOVEMBER 30, 1918
PAVING OREGON CITY TO CANBY
Engineering $ 2,444.57
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account