Construction--
Standard Bitulithic pavement, 70,170 sq.
yds. at $1.26 $ 88,414.20
Stone Shoulders, 68,208 lin. ft. at .05½ 3,751.44
Hauling and placing broken stone furnished by
State, 6,168¼ cu. yds., at $1.18 7,278.54
Broken stone, loose measure, 12,872¼ cu.
yds., at $2.37 30,507.23
Installing wooden headers at railroad crossing 24.06
Filling low places after rolling, clearing
debris after forest fire 59.53
Excavating spongy place in subgrade and
refilling 67.10
Loading and hauling to bring outside 2 ft. of
roadbed to grade; no material nearby 154.14
Grading 800 feet north from New Era, and
dismantling and loading crusher 1,726.40
-----------
Total due contractor for work done to
November 30, 1918 $131,982.64
Less 15 per cent retained pending completion 19,797.40
-----------
$112,185.24
Less plant rock and miscellaneous items
furnished by State 12,514.96
-----------
$99,670.28
----------
Total expended to November 30, 1918 $102,114.85
This work is estimated to cost complete $135,000.00
Oswego to the Multnomah County Line
On April 19, 1918, a contract was awarded by Clackamas County to the
Glemorrie Quarry Company of Oswego for the regrading of a 0.2 mile
section of the West Side Pacific Highway between Oswego and the
Multnomah County Line. At the request of the Clackamas County Court the
engineering supervision of this work was handled by the Highway
Department, Mr. M. E. DeWitt, resident engineer, on work between Oregon
City and Canby, being in charge.
This piece of work eliminated some very bad curves on the old road and
greatly improved the grade. The work was completed on September 4, 1918,
at a total cost of $5,746.68. Of this amount $507.98 was expended by the
State for the engineering. The construction cost of $5,238.70 was paid
by the County.
DETAILED EXPENDITURE STATEMENT
Grading--Multnomah County Line to Oswego
Engineering $ 507.98
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account