Third biennial report of the Oregon State Highway Commission : $b covering the period December 1st, 1916 to November 30th, 1918Benson, Simon
History
Third biennial report of the Oregon State Highway Commission : $b covering the period December 1st, 1916 to November 30th, 1918
Benson, Simon
Highway engineering -- Oregon -- History; Water resources development -- Systems engineering -- Oregon -- History
On the Clatskanie-Westport Section, which extended from Clatskanie to
the Clatsop County Line, the work was handled originally by the Warren
Construction Company, on a cost plus ten per cent. basis. The State
Highway Department took this work over December 26, 1917, and from that
time on the work was handled by this Department. This work consisted of
8.62 miles of sixteen-foot waterbound macadam.
On this section the costs show that the Warren Construction Company laid
crushed rock slightly cheaper than the State. However, the State did all
the finishing on this section, which is more expensive than laying the
base rock and it was necessary to raise the wages twenty-five per cent.
after the work was taken over by the Department. C. L. Grutze was
resident engineer on this work.
COST STATEMENT--WESTPORT-CLATSKANIE MACADAM
===========================+==========+========+==============+========
Item | Unit | Quan- | Total cost | Unit
| | tity | | cost
---------------------------+----------+--------+--------------+--------
By Warren Construction Co. | | | |
on cost plus contract-- | | | |
Clearing and grubbing | Acres | ½ | $ 49.87 | $ 99.74
Excavation | Cu. yd. | 6,200 | 6,820.70 | 1.10
6-ft. by 12-in. drain pipe | Foot | 1,085 | 2,752.38 | 2.80
Water-bound macadam |[9]Cu. yd.| 7,742 | 27,698.87 | 3.59
Engineering | | | 497.03 |
By State Forces-- | | | |
Excavation | Cu. yd. | 8,299 | 5,594.75 | .67
6-ft. by 12-in. drain pipe | Foot | 298 | 21.05 | .07
(laying) | | | |
Water-bound macadam | Cu. yd. | 17,977 | 68,168.50 | 3.79
Engineering | | | 25.09 |
| | +--------------+
Total cost | | | $ 111,628.24 |
---------------------------+----------+--------+--------------+--------
[9] 4,972 cu. yds. purchased at cost of $5,966.40, all other rock
crushed on this job.
Clatskanie-Delena Macadam
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account