Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910: The New York Tunnel Extension of the Pennsylvania Railroad.; Paper No. 1150 — John Shaqi
Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910: The New York Tunnel Extension of the Pennsylvania Railroad.; Paper No. 1150Raymond, Charles W.
History
Transactions of the American Society of Civil Engineers, Vol. LXVIII, Sept. 1910: The New York Tunnel Extension of the Pennsylvania Railroad.; Paper No. 1150
Raymond, Charles W.
Civil engineering -- Periodicals; Railroad tunnels -- Design and construction
As the facilities for the handling of freight in the Boroughs of
Brooklyn and Queens had become insufficient for taking care of the
prospective traffic, eleven new local delivery yards, having a combined
area of about 2,153 city lots, have been established, and three existing
yards are to be improved and enlarged so as to give a combined area of
about 687 city lots. Of these new yards, the Bay Ridge freight terminal,
containing about 790 city lots, is the largest; its functions have been
described above. There is a freight terminal at East New York 200 ft.
wide and a mile long, containing about 566 city lots, which will be the
distributing point of freight for the entire East New York section. This
yard is depressed, and will be crossed by six viaducts carrying city
streets. The North Shore freight yard, containing 109 city lots, is
connected with the Montauk Division by an overhead construction, known
as the Montauk Freight Cut-Off, whereby all freight traffic to Jamaica
may be kept out of the way of the Jamaica passenger traffic from the
tunnels.
It may be of interest to indicate briefly how much has already been
accomplished in the execution of this general plan, and what still
remains to be done for its completion.
The larger part of the electrification of the Long Island Railroad and
the elimination of grade crossings within the built-up city limits, the
Atlantic Avenue improvement, and the yard and piers at Greenville, have
been completed. The Sunnyside Yard and the Glendale Cut-Off will be
completed during the next twelve months. On the Tunnel and Terminal
Railroad the embankment and bridge work across the Hackensack Meadows
and all the tunnels and excavation from the west side of Bergen Hill to
Long Island City, except a short section near the eastern end of the
line, have been completed. The New York station and other buildings and
facilities connected therewith are well advanced. The laying of the
track, the electrification of the line, and the installation of the
signaling and lighting systems are under way. It is anticipated that the
line will be ready for operation in the spring of 1910.
Report has been made to the Public Service Commission that a large part
of the right of way for the New York Connecting Railroad has been
obtained, and more than $3,000,000 has been spent by this railroad. The
piers and docks at Newtown Creek and the electrification of the line
from Newark to Jersey City are not yet actively under way.
ESTIMATED COST OF THE IMPROVEMENTS.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account