Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The Bergen Hill Tunnels. Paper No. 1154Lavis, F.
History
Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The Bergen Hill Tunnels. Paper No. 1154
Lavis, F.
Civil engineering -- Periodicals; Railroad tunnels -- Design and construction
The general results of these observations show that the average time the
drills were “actually working” was 5.2 hours per shift, and that they
were actually “hitting the rock” about half of this time, or about 2.5
hours per shift. The average depth drilled per hour, during the time the
drills were “actually working,” was 2.66 ft.
The “actual working time,” as noted above, covers the period from the
time the drills were first set up in the heading after blasting until
they were taken down for the next blast; it does not include the time
occupied in setting up or taking down, which would probably average 30
min. more per shift. It is believed that this figure will also apply
very closely to drills working on the bench, though no actual
observations were taken to determine this, on account of the
irregularity with which they were worked.
The actual working time of the drills in the 736 shifts (7,360 hours)
covered by Table 1, was 3,826 hours, or 5.2 hours per shift. The average
depth drilled per yard, as shown in the last column of Table 1, agrees
fairly well with the figures on the diagrams, Figs. 1, 2, 3, and 4.
Table 2 has been compiled from detailed timed observations of individual
drilling of down holes in the bench, for periods of 7 or 8 hours each,
in January, 1907. The work at that time was in fairly normal condition
at all points.
The figures in the third column of Table 2 include the time required for
moving from one hole to another, when this occurred during the
observation, the time required for changing bits, oiling drills, etc.,
and all delays of all kinds. A close record of the delays was kept, and
it was considered that, of the 93 hours, 48 min., in Table 2, the
unnecessary delays amounted to 5 hours, 7 min., or about 5½ per cent.
TABLE 1.
#S. Number of shifts covered by observations.
#Hrs Average number of hours worked per shift.
D/Hr Average depth drilled per hour per drill.
D/Yd Average depth drilled per yard.
Hack. Hackensack
Whk. Weehawken
CS Central Shaft
Public-domain text, read in full here on John Shaqi.