Coal passers | 2 | 1.75 | 3.50 | 1 | 1.75 | 1.75 |
---------------------+-----+-------+--------+-----+-------+---------+
Totals | 334 | |$469.75 | 50 | | $108.25 |
Total daily labor expense $578.00
---------------------------------------------------------------------
The water finding its way into the side ditches in the approach, which
of course included all rain falling in this area, was intercepted just
inside the portal and carried back to the mouth of the cut through
24-in. cast-iron pipes laid beneath the conduits in the central
bench-wall, thus disposing by natural drainage of a not inconsiderable
quantity of water which would otherwise have flowed through the tunnels
to the sump at the Weehawken Shaft, from which it would have had to be
pumped to the surface.
About 100 ft. of the tunnel immediately east of the Hackensack Portal
was built by the cut-and-cover method, and the arch section used in the
tunnel was modified by widening the haunches, the thickness of the arch
at the crown being gradually increased from 22 in. at the portal,
Station 324, to 34 in. at Station 323, where the regular segmental
timbering at the tunnel commenced. A general view of the approach during
construction is shown by Fig. 1, Plate XXV.
CONTRACTOR’S ORGANIZATION.
Table 6 shows approximately the number of men employed daily on the
tunnel lining, by both the contractor and the sub-contractors, their
occupation, the average rate of wages and the total daily expense for
labor when the work was in full swing.
ENGINEERING ORGANIZATION.
The whole of the work of the North River Division was designed and
executed under the direction of Charles M. Jacobs, M. Am. Soc. C. E.,
Chief Engineer, and James Forgie, M. Am. Soc. C. E., Chief Assistant
Engineer, the construction of Section “K,” Bergen Hill Tunnels, being
directly in charge of the writer as Resident Engineer.
[Transcriber’s Note:
The two organizational charts, Figs. 20 and 21, have been reformatted
for space.]
[Chart: Fig. 20.
PENNSYLVANIA TUNNEL AND TERMINAL RAILROAD COMPANY,
SECTION “K”--BERGEN HILL TUNNELS.
Organization of Staff of Resident Engineer.
Organization Previous to the Holing Through of the Tunnels.
Resident Engineer.
_______________|________
| | |
Assistant | Assistant
Engineer. | Engineer.
_________|________ | |
| | | |
Cost and Office Field Inspection. Alignment.
Records.
Cost and Office Records.
Inspector.
Two Clerks.
Stenographer.
Telephone Operator.
Messenger.
Janitors.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account