This door is kept open to allow the
outside air to be induced up the tunnel, as the headings are at present
only 2500 yds. long, giving a resistance of not quite sufficient power
to cause the air to return. The fresh air then travels up No. 2,
crossing over the top of the “gallery of direction,” from which it is
shut off by doors, to the last cross gallery, returning by No. 1, and
finally leaving either by the “gallery of direction” or by No. 1. A
system of cooling the air and driving it on by means of a large number
of water-jets will be installed in No. 2 where that heading crosses over
the “gallery of direction,” but at present there is no need for it.
The average temperature at the face is 73° F. during the drilling
operation, 76° F. after firing the charges, and a maximum of 80° F.,
lately attaining to 86° F. on the south side, with 80° F. and 85° F.
before and after firing. The temperature of the rock is taken at every
110 yds. in holes 5 ft. deep, and shows a gradual increase according to
the depth of over-laying rock, to the conductivity of the rock, and to
the form of the mountain surface. The maximum hitherto reached on the
north side is 68° F., while on the south side, although a smaller
distance has been traversed, it attains to 79° F., due to the more rapid
increase in depth. Moreover, the temperature of the rock is observed at
the permanent stations, 550 yds. from the entrances, in its relation to
that of the tunnel and outside air, and though on the north side that of
the rock varies almost as quickly as that of the tunnel air, on the
south it is influenced very much less.
A few statistics may be of interest with regard to the progress of the
last three months (taken from the trimestrial report of January, 1900).
At Brigue, where there are three drilling-machines in No. 1 and two in
the parallel heading, the total length excavated was 995 yds. or 6409
cu. yds. in 89 working days, the average cross-sectional area being 57
sq. ft. This required 507 attacks and 3066 holes, which had a total
depth of 26,600 ft. and 14,700 re-sharpenings of the drilling-tool, with
44,000 lbs. of dynamite.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account