The average time occupied in drilling was 2 hrs. 45 mins., while
charging, firing, and clearing away the débris took 6 hrs., 35 mins. At
Brigue 648 men and 29 horses were employed at one time in the tunnel. At
Iselle the numbers were 496 men and 16 horses, working in shifts of 8
hrs. Outside the tunnel, in the shops, forges, etc., the men work 8 hrs.
to 11 hrs. per day, the total being 541 men at Brigue and 346 men at
Iselle. On the Italian side, where the rock is very much harder, there
were three drilling-machines in each heading; the total length
excavated, with a cross-sectional area of 62 sq. ft., was 960 yds. or
6700 cu. yds. in 91 working days. This required 61,293 re-sharpened
tools, 758 attacks, 7940 holes with a total depth of 33,000 ft., and
56,000 lbs. of dynamite. The average time spent in drilling was 2 hrs.
55 mins., and in charging and clearing 2 hrs. 36 mins. Thus, in the hard
gneiss, to excavate 1 cu. yd. of rock required 8¹⁄₂ lbs. of dynamite,
and each tool pierced 6¹⁄₂ ins. of rock before it required
re-sharpening.
THE MURRAY HILL TUNNEL.
The drift method of excavating tunnels was followed in Section IV of the
New York Subway, under Park Avenue between 33rd and 41st Streets. At
this point the four tracks of the subway pass under a rocky elevation,
known as Murray Hill, in two double track parallel tunnels, 43 ft.
apart, center to center. Here already existed a double track tunnel
which was built many years ago by the New York Central and Hudson River
R.R., and is now used by the Madison Avenue surface cars. The two subway
tunnels were driven close below the existing tunnel and also very near
the foundations of expensive residences along Park Avenue, particularly
on Murray Hill, one of the best residential sections of the city.
=Material Penetrated.=--The material penetrated by the excavation
consisted chiefly of a surface outcrop of the mica-schist rock which
underlies Manhattan Island. The rock was for the most part in compact
strata, dipping at about 45° from East to West, but at intervals an
unstable stratum was encountered which when free slid on the underlying
stratum. Troubles from such slides were experienced during the
construction of the tunnel.
=Cross-Section.=--The cross-section selected for the tunnels had
vertical side walls and a three-centered roof arch with the flattest
curve at the crown. The interior dimensions were 25 ft. wide and 16 ft.
high. The selected cross-section was not the best suited for a tunnel to
be driven through rock, where the sharpest curve should be at the top,
but in this case the flattened curve was chosen because of local
conditions; chiefly, the presence of the existing tunnel and the
consequent necessity of leaving a certain thickness of rock between it
and the new tunnel, without depressing very much the grade of the
subway.
[Illustration: FIG. 58.--Sequence of Excavation in the Murray Hill
Tunnel.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account