=Excavation.=--The two parallel tunnels were driven exclusively from the
ends reached by shafts; thus the tunnels were attacked at four parts. It
was in these tunnels that a comparative test was made of the different
methods of driving tunnels through rock. The contractor applied the
heading and drift method at the southern ends of the tunnels, the
eastern tunnel being driven by means of a drift while in the western
tunnel the usual heading method was followed. This latter method is
illustrated in the chapter following and the eastern tunnel at 33rd
Street, excavated by means of a drift, is here considered.
Fig. 58 shows the sequence of cuts adopted for this tunnel. It was begun
by a bottom drift, about 10 ft. high, 8 ft. wide and 7 ft. deep, which
was located at one side of the axis of the tunnel, as indicated in the
figure. This drift was immediately widened by removing the portions
marked 2. About 50 ft. in the rear the part marked 3 was taken away,
thus clearing the entire lower portion of the tunnel. Section 4, about
50 ft. to the rear of section 3, was then broken down and removed.
The methods of drilling and blasting were as follows: In taking out the
original drift, a wedge-shaped center cut was made and then enlarged to
the full size of the drift by drilling parallel holes. The succeeding
sections, 2 and 3, were removed by driving parallel holes, while the top
section, 4, was taken away by a center cut and parallel holes. The
drills were mounted on columns, two drills to a column, and the holes
were usually drilled about 7 ft. deep, starting with a diameter of 2³⁄₄
in. and ending with a diameter of 1³⁄₄ in. They were blasted with 40%
dynamite in light charges, only a few holes being fired at a time,
usually not more than three or four.
[Illustration: FIG. 59.--Traveling Platform for the Excavation of the
Upper Side of the Murray Hill Tunnel.]
To remove section 4, a traveling platform 10¹⁄₂ ft. long and 25 ft. wide
was used. This platform, as shown in Fig. 59, consisted of two
longitudinal beams mounted on four double flanged wheels which were
running on tracks laid 23 ft. apart. Resting on top of these beams were
four 12 in. × 12 in. uprights braced in every direction against the
framework of the platform. This frame was built of 12 in. × 12 in. beams
laid longitudinally, the transverse beams being 12 in. × 14 ins. The
platform proper was made of 3 in. planks, and was set 9 ft. above the
tunnel floor. The columns supporting the drills for the excavation of
the upper section 4, were set up above the platform which was then
reinforced by other vertical props, as indicated by the dotted lines in
the figure. These props, however, were placed so as to leave a clearance
beneath the platform for the cars to carry away the débris from the
front. During the blasting the platform was moved back so that the
blasted rock fell to the floor of the tunnel, whence it was loaded into
boxes on the cars.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account