The Baltimore Belt Ry. Co. was organized in 1890 by officials of the
Baltimore & Ohio, and Western Maryland railways, and Baltimore
Capitalists, to build 7 miles of double track railway, mostly within the
city limits of Baltimore. This railway was partly open cut and
embankment, and partly tunnel, and its object was to afford the
companies named facilities for reaching the center of the city with
their passengers and freight. To carry out the work the Maryland
Construction Co. was organized by the parties interested, and in
September, 1890, this company let the contract for construction to Ryan
& McDonald of Baltimore, Md. The chief difficulties of the work centered
in the construction of the Howard-street tunnel, 8350 ft. long, running
underneath the principal business section of the city.
=Material Penetrated.=--The soil penetrated by the tunnel was of almost
all kinds and consistencies, but was chiefly sand of varying degrees of
fineness penetrated by seams of loam, clay, and gravel. Some of the
clay was so hard and tough that it could not be removed except by
blasting. Rock was also found in a few places. For the most part,
however, the work was through soft ground, furnishing more or less
water, which necessitated unusual precautions to avoid the settling of
the street, and consequent damage to the buildings along the line. A
large quantity of water was encountered. Generally this water could be
removed by drainage and pumps, and the earth be prevented from washing
in by packing the space between the timbering with hay or other
materials. At points where the inflow was greatest, and the earth was
washed in despite the hay packing, the method was adopted of driving
6-in. perforated pipes into the sides of the excavation, and forcing
cement grout through them into the soil to solidify it. These pipes
penetrated the ground about 10 ft., and the method proved very efficient
in preventing the inflow of water.
=Excavation.=--The excavation was carried out according to the German
method of tunneling. Bottom side drifts were first driven, and then
heightened to the springing line of the roof arch. Next a center top
heading was driven, and the haunch sections taken out. The object of
beginning the excavations by bottom side drifts, was to drain the soil
of the upper part of the section. The center core was removed after the
side walls and roof arch were completed, its removal being kept from 50
ft. to 75 ft. to the rear of the advanced heading. The dimensions of the
side drifts proper were about 8 × 8 ft., but they were often carried
down much below the floor level to secure a solid foundation bed for the
side walls.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account