FIG. 90.--Temporary Timbering of the Roof in the American Method.]
[Illustration: ~Section E-F.~
FIG. 91.--Showing Crown Bars Supported by Segmental Arches.]
=Excavation.=--The diagram in Fig. 88 shows the sequence of excavation.
The work begins by driving a central heading usually 7 × 8 ft., strutted
by means of vertical or batter posts and cap-piece. Fig. 89,[11] the
props resting on foot blocks. Between the cap-pieces of the consecutive
frames are placed planks driven upward at a slightly inclined angle.
After the heading has been excavated and strutted, the floor is lowered
by removing the part marked 2 in the figure. The two batter posts
supporting the cap-piece are now substituted by two longer ones resting
on the floor of part 2 and abutting against longitudinal beams which
are inserted underneath the cap-pieces. These longitudinal beams are
called crown bars. The new batter posts are resting either on foot
blocks or sills according to the quality of soil and they are strongly
wedged to the crown bars. On each side of these crown bars are inserted
poling-boards or planks close to each other, which are driven downward.
The part marked 3 in the figure is removed by enlarging the cut 1 × 2 on
both sides. The plank, inserted above the crown bar, is driven in either
preceding or following the excavation and another crown bar is inserted
at the end of this plank. This second crown bar is supported by a prop
whose other end abuts against the foot of the rafter strutting the
heading. Between this crown bar and the roof of the excavation, other
planks are placed transversally to the axis of the tunnel and are driven
in until they are supported by a new crown bar, etc. The various props
supporting the crown bars are placed radially or in a fan-like manner,
similar to the characteristic arrangement of the timbering in the
Belgian method. Bracers to strengthen the timbering and the roof of the
excavation are inserted longitudinally between the various posts and
transversally between the crown bars, Fig. 90. As a rule, only three or
four of these radial structures are temporarily erected. A trench is
excavated at the side of the part marked 3 in the figure to receive the
wall plate which is a heavy timber laid on the floor parallel to the
longitudinal axis of the tunnel. On the wall plates are erected the
arched timber sets composed of five or seven segments of hewn timbers so
as to form a polygonal frame which is wedged to the crown bars and
which will support the arch of the roof. After one of these segmental
timber sets is erected the temporary radial structure is removed and the
upper section of the tunnel is cleared of any obstruction as the
pressures are transferred to the wall plates, Fig. 91. The bench marked
4 in the figure is taken away and the vertical props inserted under the
wall plates, Fig. 92.
[11] Figs. 89 to 91 are taken from a paper by S. W. Hopkins in
_Harvard Engineering Journal_, April, ’03, on the Fort George tunnel.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account