=Hauling.=--The excavation of the heading and the upper section of the
tunnel is usually far ahead of the bench, consequently the hauling of
both the débris and the building materials is made at two different
levels, viz., on the bench and on the floor of the tunnel. When the face
of the heading and the excavation of the bench are not more than 50 ft.
apart, the hauling can be conveniently done on the tunnel floor, while
the materials and débris on the upper section of the tunnel are hauled
by wheelbarrows or light cars propelled by handpower. For a greater
distance, however, it is more convenient to use light cars running on
narrow-gauge tracks all through the tunnel. In this case the tracks on
the tunnel floor and on top of the bench are connected by means of an
inclined platform where the cars may ascend and descend without
interfering with the excavation of the bench. Here, as a rule, tunnels
have been excavated in soils considered good, generally through rock,
while loose soils have been encountered only in small sections. The same
method of excavation for whatever material is encountered is certainly
very convenient, as it affords a great regularity in the work; hence its
extensive use. A great disadvantage of this method is the double
strutting, viz., the polygonal and the longitudinal strutting succeeding
each other, whereas one of them could be easily spared. Another defect
is that it requires a larger amount of excavation, in case the strutting
is left in place.
AUSTRIAN METHOD.
The Austrian full-section method of tunneling through soft ground was
first used in constructing the Oberau tunnel on the Leipsic and Dresden
R.R., in Austria in 1837. It consists in excavating the full section and
building up the lining masonry from the foundations as in the English,
but with the important exception that the invert is built last instead
of first in all cases except where the presence of very loose soil
requires its construction first. A still more important difference in
the two methods is that the excavation is carried out in smaller
sections and is continuous in the Austrian method instead of alternating
with the mason work as it does in the English method.
=Excavation.=--The excavation in the Austrian method begins by driving
the bottom center drift No. 1, Fig. 93, rising from the floor of the
tunnel section nearly to the height of the springing lines of the roof
arch. When this drift has been driven ahead a distance varying from 12
ft. to 20 ft. or sometimes more, the excavation of the center top
heading No. 2 is driven for the same distance. The next operation is to
remove part No. 3, thus forming a central passage the full depth of the
tunnel section at the center. This trench is enlarged by removing parts
Nos. 4, 5, 6, 7, and 8 in the order named until the full section is
opened. A modification of this plan of excavation is shown by Fig. 94
which is used in firm soils.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account