=Hauling.=--The system of hauling adopted with this method of tunneling
is very simple, since the excavation of the various parts is driven only
from 6 ft. to 10 ft. ahead, and the work progresses slowly to allow for
the construction of the heavy strutting required. To take away the
material from the center bottom drift, narrow-gauge tracks carried by
cross-beams between the side posts above the floor line are employed.
This same narrow-gauge line is employed to take away a portion of parts
No. 2, the remaining portion being left and used for the refilling after
the bottom portion of the lining has been built, as previously
described. The upper half of the section being excavated, as in the
Belgian method, the system of hauling with inclined planes to the tunnel
floor below, which is a characteristic of that method, may be employed.
It is the more usual practice, however, since the excavation is carried
so little a distance ahead and progresses so slowly, to handle the spoil
from the upper part of the section by wheelbarrows which dump it into
the cars running on the tunnel floor below. Hand labor is also used to
raise the construction materials used in building the upper section. The
tracks on the tunnel floor, besides extending to the front of the
advanced bottom center drift, have right and left switches to be
employed in removing the refilling in parts No. 2, the spoil from the
upper part of the section, and the material of part No. 7. Fig. 103 is a
longitudinal section showing the plan of excavation and strutting
adopted with the Italian method.
[Illustration: FIG. 103.--Sketch Showing Longitudinal Section of a
Tunnel under Construction, Italian Method.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account