The excavation of the upper half of the tunnel section is strutted as in
the Belgian method, with radial struts carrying longitudinal roof bars
and transverse poling-boards. On account of the enormous pressures
developed by the treacherous soils in which only is the Italian method
employed, the radial strutting frames and crown bars must be of great
strength, while the successive frames must be placed at frequent
intervals, usually not more than 3 ft. After the masonry side walls have
been built in the lower part of the excavation, longitudinal planks are
laid against the side posts of the center bottom drift frames, to form
an enclosure for the filling-in of parts No. 2. The object of this
filling is principally to prevent the squeezing-in of the side walls.
[Illustration: FIGS. 101 and 101A.--Sketches Showing Construction of
Centers, Italian Method.]
=Centers.=--Owing to the great pressures to be resisted in the
treacherous soils in which the Italian method is used, the construction
of the centers has to be very strong and rigid. Figs. 101 and 101A show
two common types of center construction used with this method. The
construction shown in Fig. 101 is a strong one where only pressures
normal to the axis of the tunnel have to be withstood, but it is likely
to twist under pressures parallel to the axis of the tunnel. In the
construction shown by Fig. 101A, special provision is made to resist
pressures normal to the plane of the center or twisting pressures, by
the strength of the transverse bracing extending horizontally across the
center.
[Illustration: FIG. 102.--Sketch Showing Invert and Foundation Masonry,
Italian Method.]
=Masonry.=--The construction of the masonry lining begins with the
invert, as indicated by Fig. 100, and is carried up to the roof of parts
No. 2, as already indicated, and is then discontinued until the upper
parts Nos. 4, 5, and 6 are excavated. The next step is to sink side
trenches at the ends of part No. 7, which reach to the top of the
completed side walls. This operation leaves the way clear to finish the
side walls and to construct the roof arch in the ordinary manner of such
work in tunneling. Since this method of tunneling is used only in very
soft ground which yields under load, the usual practice is to construct
the invert and side walls on a continuous foundation course of concrete
as indicated by Fig. 102. The lining is usually built in successive
rings, and the usual precautions are taken with respect to filling in
the voids behind the lining. The thickness of the lining is based upon
the figures for laminated clay of the third variety given in Table II.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account