Subways are usually constructed under and along important streets where
electric cars are running. The engineers have taken advantage of the
presence of these lines to facilitate the construction of subways. In
New York, for instance, the tracks of the electric lines were supported
by cast-iron yokes 4 or 5 ft. apart and were surrounded by concrete,
leaving only a large hollow space in the middle for the wires and
trolleys. The rails from 40 to 60 ft. long formed almost a solid
concrete structure for their entire length. The tracks and the street
surface were supported by horizontal beams inserted underneath the
tracks. These were the caps of bents constructed underground whose
rafters were finally resting on the subgrade of the proposed subway.
The various methods for constructing the subways may be classified as
follows: (1) The single wide trench method; (2) the single narrow
longitudinal trench method; (3) the parallel longitudinal trench method;
(4) the slice method.
=Single Longitudinal Trench.=--The simplest manner by which to construct
open-cut tunnels is to open a single cut or trench the full width of the
tunnel masonry. This trench is strutted by means of side sheetings of
vertical planks, held in place by transverse braces extending across the
trench and abutting against longitudinal timbers laid against the
sheeting plank. The lining is built in this trench, and is then filled
around and above with well-rammed earth, after which the surface of the
ground is restored. An especial merit of the single longitudinal trench
method of open-cut tunneling is that it permits the construction of the
lining in a single piece from the bottom up, thus enabling better
workmanship and stronger construction than when the separate parts are
built at different times. The great objection to the method when it is
used for building subways under city streets is, that it occupies so
much room that the street usually has to be closed to regular traffic.
For this reason the single longitudinal trench method is seldom
employed, except in those portions of city subways which pass under
public squares or parks where room is plenty.
This method was followed in the construction of the New York subway,
Section 2, along Elm St., a new street to be opened to traffic after the
subway had been completed, and at other points where local conditions
allowed it.
[Illustration: FIG. 112.--Diagram Showing Sequence of Construction in
Open-Cut Tunnels.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account