The bottom is excavated so as to conform to the exterior
lines of the masonry. The excavation follows so closely to the outer
lines of the normal section of the tunnel that very little loss occurs,
even in bad material; and there is no loss where sufficient bond exists
in the material to hold it in place until the poling-boards are in
position.
[Illustration: ~Bracing.~
~Arch Construction.~
~Longitudinal Section.~
FIG. 111.--Sketch Showing Pilot Method of Tunneling.]
In the Brooklyn sewer tunnel work, previously mentioned, the pilot was
built of steel plates ³⁄₈ in. thick, 12 ins. wide, and 37¹⁄₂ ins. long,
rolled to a radius of 3 ft. Steel angles 4 × 4¹⁄₂ ins. were riveted
along all four sides of each plate, and the plates were bolted together
by ³⁄₄-in. machine-bolts. The plates weighed 136 lbs. each, and six of
them were required to make one complete ring 6 ft. in diameter. In
bolting them together, iron shims were placed between the horizontal
joints to form a footing for the wooden braces for the shell, which
radiate from the pilot. The shell plates of the 15-ft. section of the
tunnel were of No. 10 steel 12 ins. wide and 37 ins. long, with steel
angles 2¹⁄₂ × 2¹⁄₂ × ³⁄₈ ins., riveted around the edges the same as for
the pilot, and put together with ⁵⁄₈-in. bolts. These plates weighed 61
lbs. each, and eighteen of them were required to make one complete ring
15 ft. in diameter. The plates for the 12-ft. section were No. 12 steel
12 ins. wide with 2 × 2 × ¹⁄₄-in. angles. Seventeen plates were required
to make a complete ring.
CHAPTER XVI.
OPEN-CUT TUNNELING METHODS; TUNNELS UNDER CITY STREETS; BOSTON SUBWAY
AND NEW YORK RAPID TRANSIT.
OPEN-CUT TUNNELING.
When a tunnel or rapid-transit subway has to be constructed at a small
depth below the surface, the excavation is generally performed more
economically by making an open cut than by subterranean tunneling
proper. The necessary condition of small depth which makes open-cut
tunneling desirable is most generally found in constructing
rapid-transit subways or tunnels under city streets. This fact
introduces the chief difficulties encountered in such work, since the
surface traffic makes it necessary to obstruct the streets as little as
possible, and has led to the development of the several special methods
commonly employed in performing it.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account