Another modification of the parallel longitudinal trenches method was
used in the construction of the New York subway. A narrow longitudinal
trench was excavated on one side of the street near the sidewalk.
Meanwhile the pavement of half of the street was removed and a wooden
platform of heavy planks, supported by longitudinal beams which were
buried in the ground, was substituted. Then small cuts underneath the
car tracks were directed from the side trench and heavy beams or needles
were placed in these cuts, which also reached the longitudinal beams of
the wooden platform. The needles were wedged and blocked to the car
track structure and the beams. They were temporarily supported by cribs
built from underneath as the excavation progressed. When the subgrade
was reached, vertical and batter posts were inserted to support the
needles, thus forming regular timber bents underground. In the space
thus left open the subway was constructed to the middle of the street.
While the work was going on as described, another longitudinal narrow
trench was excavated at some distance on the other side of the street.
From this trench, the work of constructing the other half of the subway
was carried on in the manner just described. After the work had been
completed, the timbers removed, the voids filled in and the pavement of
the street restored, another equal section was attacked on both sides of
the street.
=Transverse Trenches.=--The transverse trench or “slice” method of
open-cut tunneling has been employed in one work, the Boston Subway.
This method is described in the specifications for the work prepared by
the chief engineer, Mr. H. A. Carson, M. Am. Soc. C. E., as follows:--
“Trenches about 12 ft. wide shall be excavated across the street to as
great a distance and depth as is necessary for the construction of the
subway. The top of this excavation shall be bridged during the night by
strong beams and timbering, whose upper surface is flush with the
surface of the street. These beams shall be used to support the railway
tracks as well as the ordinary traffic. In each trench a small portion
or slice of the subway shall be constructed. Each slice of the subway
thus built is to be properly joined in due time to the contiguous
slices. The contractor shall at all times have as many slice-trenches in
process of excavation, in process of being filled with masonry, and in
process of being back-filled with earth above the completed masonry, as
is necessary for the even and steady progress of the work towards
completion at the time named in the contract.”
In regard to the success of this method Mr. Carson, in his fourth annual
report on the Boston Subway work, says:
“The method was such that the street railway tracks were not disturbed
at all, and the whole surface of the street, if desired, was left in
daytime wholly free for the normal traffic.”
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account