All the concrete masonry of the roof, foundations, and side walls
contains a layer of waterproofing, so as to keep perfectly dry the
underground road, and prevent the percolation of water. This
waterproofing is made up as follows: On the lowest stratum of concrete,
whose surface is made as smooth as possible, a layer of hot asphalt is
spread. On this asphalt are immediately laid sheets or rolls of felt;
another layer of hot asphalt is then spread over the felt, and then
another layer of felt laid, and so on, until no less than two, and no
more than six, layers of felt are laid, with the felt between layers of
asphalt. On top of the upper surface of asphalt the remainder of the
concrete is put in place so as to reach the required thickness of the
concrete wall.
[Illustration: FIG. 120.--Park Avenue Deep Tunnel Construction, New York
Rapid Transit Railway.]
_Tunnels._--When the distance between the roof of the proposed structure
and the street was 20 ft. or over, the Standard Subway construction was
replaced by tunnels. Three important tunnels have been constructed along
the line of the New York Rapid Transit and these are located between 33d
and 42d Streets on Park Ave., under Central Park northeast of 104th St.
and under Broadway north of 152d St. The Park Ave. construction (Fig.
120) consists of two parallel double-track tunnels, located on each side
of the street, and about 10 ft. below the present tunnel. The soil being
composed of good rock, the tunnels were driven by a wide heading, and
one bench, since no strutting was required, and the masonry lining, even
of the roof, was left far behind the front of the excavation. The
masonry lining consists of concrete walls and brick arches. The tunnels
under Central Park and under Broadway being driven through a similar
rock, the same method of excavation and the same manner of lining was
used.
The tunnel under the Harlem River was driven through soft ground; and it
was constructed as a submarine tunnel, according to the caisson process.
The tunnels were lined with iron made up of segments, with radial and
circumferential flanges. Concrete was placed inside and flush with the
flanges.
[Illustration: FIG. 121.--Harlem River Tunnel, New York Rapid Transit
Railway.]
The tracks, both in the subway and tunnels, are an intimate part of the
concrete flooring. The rail rests on a continuous bearing of wooden
blocks, laid with the grain running transversely with respect to the
line of the rail, and held in place by two channel iron guard rails. The
guard rails are bolted to metal cross-ties embedded in the concrete.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account