The question now arose what it was best to do. It was impracticable to
use a shield, as the material ahead of the break required blasting, and
the pressure from above was enormous. On account of its expense and
difficulty of application the freezing process did not seem advisable,
and the plenum process was likewise out of the question on account of
the great pressure which would be required at this depth. The détour to
the south which had been made by the contractor had been unsuccessful,
and had left the ground in a treacherous condition. To depress the
tunnel was not advisable, for it was not by any means certain that the
bed of gravel could be avoided in that way; and, moreover, it would be
necessary to ascend again further on, and thus leave a trap which would
effectually cut off escape to those at work on the face if water again
broke into the tunnel.
It was finally decided that the old plan of deflecting the line toward
the north and upward so as to pass over the underground stream should be
tried. A hole was therefore cut through the tunnel lining 1433 ft. from
the shore, and work was begun on a détour of 20° toward the north and an
upward grade of 10%. Fair progress was made on this new line, gradually
ascending into solid rock, until May 10, when the test borings, which
were constantly made in every direction from the face, showed that sand
was being approached. A brick bulkhead was therefore built into the
masonry as a safeguard, should it happen that water was encountered in
large quantities. As the borings seemed to indicate that the top surface
of the rock underlying the sand was nearly level, the lower half of the
tunnel was first excavated, leaving about 18 ins. of the rock to serve
as a roof (Sketch _a_, Fig. 123), and the brick invert was built for a
distance of 52 ft. The rock roof was then carefully broken through for
short distances at a time, and short sheeting driven ahead into the
sand, which proved to be a very fine quicksand flowing through the
smallest openings. Extreme care had to be taken in this work, but little
by little the brickwork was pushed ahead until at a distance of 90 ft.
from the point where the sand was first met, and 208 ft. from the old
tunnel, the sand stopped and the heading entered a hard clay.
All this work had been done on an ascending grade, and the ascent was
continued about 40 ft. farther in the clay. By this time a sufficient
elevation was gained to pass over the underground stream, and the tunnel
line was changed to head toward the lake shaft, and the grade reduced to
a level. The underground stream was passed without trouble and the
tunnel continued for a distance of 54 ft. without difficulty. On July 10
the clay in the heading suddenly softened, and before the miners could
secure it by bracing, the water rushed in, followed by gravel, filling
up solidly some 34 ft. of the tunnel before it was stopped by a timber
bulkhead hastily built.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account