This disaster delayed the work for some time, but in June the
contractors erected a new building and new machinery, and resumed work.
Very little progress was made; and the air escaped so rapidly that it
loosened the sand surrounding the shaft and reduced the friction to such
an extent that on July 28 the entire cylinder lifted bodily about 6 ft.,
and sand rushed in, filling the lower part of the cylinder to within 45
ft. of the lake surface. No further work was done by the contractors
although they submitted a proposition to sink a steel cylinder inside
the cast-iron cylinder and extending from 5 ft. above datum to 100 ft.
below datum for $300 per ft. This proposition was refused by the city;
and since work on the tunnel proper had been abandoned by the
contractors some time before, as had already been described, the city
suspended their contract on Oct. 19.
On Oct. 30 a contract was made with Mr. Thos. Murphy of Milwaukee, Wis.,
to sink a steel cylinder inside the old iron cylinder. The water was
first pumped out of the old cylinder, and a timber bulkhead built at
the bottom. On this the steel cylinder was built, and then the bulkhead
was removed. Air pressure was put on, and the excavation proceeded
successfully until the bottom layer of clay was met with, when all
chances for trouble ceased.
The cylinder, as it was completed, penetrated 9 ft. into the hard clay,
and was underpinned with brickwork for a depth of 29 ft. or more, to a
point 4 ft. below the grade line of the tunnel. At the lower end, the
section of the shaft was changed from a circle to a square. Later the
steel cylinder was lined with brick.
On March 28, 1894, an agreement was made with Mr. Thos. Murphy to
construct the tunnel from the lake shaft toward the shore. Except that
considerable water was encountered, which, owing to inadequate pumping
machinery, filled the tunnel and shaft at two different times, and had
to be removed, no very great difficulty was had with this part of the
work.
On July 28, 1895, the headings from the lake and shore shafts met.
Meanwhile the cast-iron pipe intake, the intake crib, etc., had been
completed, and practically all that remained to be done was to clean the
tunnel and lift the pumping machinery at the shore shaft. During the
cleaning, the air pressure had been kept up on account of the leakage
through the brick lining, and, indeed, the pressure was kept up until
the last possible moment, and everything made ready for removing the
air-locks, bulkheads, pumps, etc., in the least possible time. The pumps
were the last to come out.
CHAPTER XIX.
SUBMARINE TUNNELING (Continued).
THE SHIELD SYSTEM.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account