Meanwhile, a different set of afflictions had come upon the engineer and
contractors in sinking the lake shaft and driving the heading toward
shore. This shaft was intended to be built by sinking a cast-iron
cylinder 10 ft. in diameter, made up of sections bolted together. Work
was begun July 5, 1892, and the sinking was accomplished first by
weighting the cylinder, and afterwards by pumping out the sand and water
within it until the pressure from the outside broke through under the
cutting edge and forced the sand into the cylinder, allowing it to sink
a little. From 10 to 30 cu. yds. of sand were carried into the cylinder
each time, and finally it was feared that if the process continued, the
crib, which had been previously erected, would be undermined. On Sept.
6, therefore, the contractors were ordered to discontinue this method of
work. No change was made, however, until Oct. 1, when the cylinder had
reached a depth of 68 ft., and by this time there was quite a large
cavity underneath the crib. This was refilled, and the cylinder pumped
out, and excavation begun inside of it. On Oct. 11 a 2¹⁄₂-ft. deep ring
of brickwork was laid underneath the cutting edge; but in trying to put
in another ring beneath the first, two days later, the sand and water
broke through the bottom, driving the men out, and filling the cylinder
to a depth of 16 ft. with sand. The pumps were started, but the water
could not be lowered to a greater depth than 60 ft.
At the request of the contractors, the city engineer had a boring made
at the center of the shaft to determine the character of the material to
be further penetrated. This boring showed that sand mixed with loam and
gravel would be found for a depth of 26 ft., then would come 15 ft. of
red clay, and finally a layer of hard clay like that penetrated by the
shore end of the tunnel. About the middle of December the contractors
made another attempt to pump the shaft, but finding that the water came
in at the rate of 25 gallons a minute, abandoned the attempt. In the
latter part of February preparations were made to put an air-lock in the
shaft and use compressed air. Hardly had the work been begun by this
system when, on April 20, 1893, a terrific easterly storm swept the top
of the crib bare of the buildings and machinery, and drowned all but one
of the 15 men at work there.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account