=Air Locks.=--Two bulkhead walls, forming the rear closure of the
pneumatic sections, were built in each end of each tunnel, one just
ahead of the shield chamber, the other about 1200 ft. ahead of the
first. The walls were built of Portland concrete 10 ft. thick, and they
were grouted with Portland cement, under a pressure of nearly 100 lbs.
per sq. in., to make them thoroughly air-tight. Each wall had in it
three locks; for man, material and emergency. Each was equipped with
hand valves arranged to be operated from either outer end or from
within. The floors of the man and material locks were on a level with
the working platform of the tunnel, about 3 ft. 6 ins. above the invert;
the floor of the emergency lock was about 5 ft. above the horizontal
axis of the tunnel. The locks were made of steel plates and shapes, with
iron fittings riveted and bolted together. The man lock was 11 ft. long
of elliptical cross-section, 6 ft. vertical diameter and 5 ft.
horizontal; the material lock was 25 ft. long, with circular
cross-section, 7 ft. diameter, and the emergency lock was 20 ft. long,
of elliptical cross-section, 4 ft. vertical and 3 ft. horizontal
diameters. Fig. 139 shows the elevation of the air lock used in the
Pennsylvania tunnel.
[Illustration: ~Sectional Elevation~
~Horizontal Section~
FIG. 139.--Plan and Elevation of First Bulkhead Wall in South Tube
Manhattan.]
=Excavation.=--In driving these tunnels almost any kind of material was
encountered, viz., rock, partly rock, and partly loose soil, sand and
gravel, and finally silt.
=Rock.=--Much of the rock excavation was made before the shields were
erected in order to avoid the handling of rock through the narrow
openings of the shield doors. Throughout the cross-section the shield
traveled on a cradle of concrete in which 2 or 3 steel rails were
imbedded. At the points where the excavation had been made for the full
section of the tunnel, it was only necessary to trim off the projecting
corners of rock. Where only the bottom heading had been driven the
excavation was completed just in front of the shield; the drilling below
the axis level being done from the heading itself, and above that from
the front sliding platforms of the shield. The holes were placed near
together and were drilled short; very light charges of powder were used
in order to lessen the chance of knocking the shield about too much.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account