The arch was built up from the springing lines on both sides at the same
time, four masons being employed. The rings were built beginning with
the intrados, which was brought up, say, a distance of about 2 ft. from
the springing line. Then the back of the ring was well plastered with
from ³⁄₈ in. to ¹⁄₂ in. of mortar, and the second ring brought up to the
same height and plastered on the back, and so on until the last ring was
laid. After bringing the full width of the arch up some distance, new
laggings were placed on the ribs for an additional height of 2 ft. and
the same process was repeated. All the space between the extrados of the
masonry arch and the old lining was compactly filled with dry rubble.
When high enough so that the hip segments had a foot or more bearing on
the masonry the segments were securely wedged and blocked up against the
brickwork, and the longitudinal 4 × 6 in. timbers removed. The
remaining space was now clear for completion of the arch, and both sides
were brought up until there was not sufficient space for four masons to
work, when the keying was completed by two masons beginning at the
completed and working back toward the toothed end. The brickwork was
built from the top of a staging-car.
[Illustration: ~Cross Section.~
~Longitudinal Section.~
FIG. 162.--Relining Timber-Lined Tunnel, Great Northern Ry.]
In a few instances where slides occurred after the removal of the slide
timbering, the method of re timbering the tunnel shown in Fig. 162 was
adopted. Two side drifts were first run 2¹⁄₂ ft. wide by 4 ft. high, and
the plate timbers placed in position and blocked. Cross drifts were then
run, and the roof segments placed, and the core down to the level of the
bottoms of the side drifts taken out. The lower wall plates were then
placed and the hip segments inserted. The bench was then taken down by
degrees, the side plates being held by jacks, and the posts placed one
at a time. As the masonry at the points where slides occur consists of
30-in. walls and six-ring arch, the timbering was 22 ft. wide in the
clear, with other dimensions as shown in Fig. 162.
Only a single crew of brick and stone masons was employed. In order to
prepare the sections for these masons it was necessary to have timber
and trimming crews at work throughout the whole day of 24 hours, so that
an engine and two train crews were in constant attendance. The single
mason crews were able to complete 8 ft. of side wall and arch in 24
hours. The number of men actually employed at the tunnel was 35. This
included electric-light maintenance, and all other labor pertaining to
the work. The tunnel was lighted by an Edison dynamo of 20 arc light
capacity, one arc light being placed on each side of the tunnel at all
working-places. Each lamp carried a coil of wire 20 or 30 ft. long to
allow it to be shifted from place to place without delay.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account