(3) When the center line of the entire tunnel is a curve, there is more
probability of slight deviations from the true axis of the proposed
work. In such a case it would be advisable to first excavate a narrow
heading and to concentrate all the efforts in driving the headings as
rapidly as possible in order that they may meet in the shortest time.
The center line of these headings is staked out by the usual method of
the offsets from the tangent. The enlarging of the section of the tunnel
could be commenced at both portals and be driven slowly until the
headings have met and any errors corrected, when the work could be
pushed with the greatest activity all along the line.
(4) In corkscrew or helicoidal tunnels the entire center line is on a
curve. In these tunnels, as a rule, there is a great difference of level
between the two portals, one being much higher than the other, so
careful attention should be paid to the tunnel grade. Working in the
limited spaces afforded by narrow headings it is very probable that
errors may be made in fixing both the alignment and the grade of the
tunnel. To prevent these almost unavoidable errors, it would be well to
excavate at first only the headings, to stake the center line in the
roof of these headings and then to lay the grade of the tunnel as
accurately as possible. The work on the headings should be pushed as
rapidly as possible in order that they may meet quickly, so that the
center line, as temporarily laid out, may be corrected and permanently
fixed for the direction of successive operations. In these tunnels the
headings should be excavated near the center of the tunnel cross-section
so that the sides and roof of the heading would be at some distance from
the sides and roof of the proposed tunnel. This arrangement will easily
permit corrections to be made in case any slight difference from the
true line was erroneously made during the excavation of the headings.
FORM AND DIMENSIONS OF CROSS-SECTION.
In deciding upon the sectional profile of a tunnel two factors have to
be taken into consideration: (1) The form of section best suited to the
conditions, and (2) the interior dimensions of this section.
=Form of Section.=--The form of the sectional profile of a tunnel should
be such that the lining is of the best form to resist the pressures
exerted by the unsupported walls of the tunnel excavation, and these
vary with the character of the material penetrated. These pressures are
both vertical and lateral in direction; the roof, deprived of support by
the excavation, tends to fall, and the opposite sides for the same
reason tend to slide inward along a plane more or less inclined,
depending upon the friction and cohesion of the material. In some rocks
the cohesion is so great that they will stand vertically, while it may
be very small in loose earth which slides along a plane whose
inclination is directly proportional to the cohesion.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account