It may be questioned whether the engineers of the town were justified in
passing the contract with Kind to finish the work within the time, and
for the sum at which he undertook it; but they certainly treated him
with kindness and consideration, in allowing him to conduct the work at
the expense of the city of Paris, for so long a period after the
expiration of his contract. It seems, however, that the French
well-borers could not at the time have attempted to continue the well
upon any other system than that introduced by Kind; that is to say, upon
the supposition that it should be completed of the dimensions originally
undertaken. Experience has shown that both steining and tubing were
badly executed at the well of Passy. The masonry lining was introduced
after Kind's contract had expired, and when he had ceased to have the
control of the works; the wrought-iron tubing at the lower part of the
excavation being a subsequent idea. It has followed from this defective
system of tubing--the wood necessarily yielding in the vertical
joints--that the water in its upward passage escaped through the
joints, and went to supply the basement beds of the Paris basin, which
are as much resorted to as the London sand-beds for an Artesian supply;
and, in fact, the level of the water has been raised in the neighbouring
wells by the quantity let in from below, and the yield of the well
itself has been proportionally diminished, until it has fallen to
450,000 gallons a day. That the increased yield of the neighbouring
wells is to be accounted for by the escape of the water from the
Artesian boring is additionally proved by the temperature of the water
in them; it is found to be nearly 82° Fah., or nearly that observed in
the water of Passy. This was an unfortunate complication of the bargain
made between Kind and the Municipal Council; but it in no respect
affects the choice of the boring machinery, which seems to have complied
with all the conditions it was designed to meet. The descent of the
tubes and their nature ought to have been the subject of special study
by the engineers of the town, who should have known the nature of the
strata to be traversed better than Kind could be supposed to do, and
should have insisted upon the tubing being executed of cast or
wrought-iron, so as effectually to resist the passage of the water. At
any rate, this precaution ought to have been taken in the portions of
the well carried through the basement beds of the Paris basin, or
through the lower members of the chalk and the upper greensand.
[Illustration: WELL AT PONDERS END.
Figs. 267, 268.]
_Ponders End_, Middlesex.--At the works of the London Jute Company. It
will be seen from the Figs. 267, 268, that this well is bored all but
the top 4 feet, which is 5 feet across and steined with 9-inch work. The
uppermost tube is 12 inches in diameter, decreased to 9 inches, and then
to 8 inches, and ending with a 6-inch bore, unlined, in the chalk.
The strata passed were;--
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account