To sink a well by underpinning, an excavation is first made to such a
depth as the strata will allow without falling in. At the bottom of the
excavation is laid a curb, that is, a flat ring, whose internal diameter
is equal to the intended clear diameter of the well, and its breadth
equal to the thickness of the brickwork. It is made of oak or elm planks
3 or 4 inches thick, either in one layer fished at the joints with iron,
or in two layers breaking joint, and spiked or screwed together. On
this, to line the first division of the well, a cylinder of brickwork,
technically called steining, is built in mortar or cement. In the centre
of the floor is dug a small pit, at the bottom of which is laid a small
platform of boards; then, by cutting notches in the side of the pit,
raking props are inserted, their lower ends abutting against a foot
block, and their upper ends against the lowest setting, so as to give
temporary support to the curb with its load of brickwork. The pit is
enlarged to the diameter of the shaft above; on the bottom of the
excavation is laid a new curb, on which is built a new division of the
brickwork, giving permanent support to the upper curb; the raking props
and their foot-blocks are removed; a new pit is dug, and so on as
before. Care should be taken that the earth is firmly packed behind the
steining.
A common modification of this method consists in excavating to such a
depth as the strata will admit without falling in. A wooden curb is laid
at the bottom of the excavation, the brick steining laid upon it and
carried to the surface. The earth is then excavated flush with the
interior sides of the well, so that the earth underneath the curb
supports the brickwork above. When the excavation has been carried on as
far as convenient, recesses are made in the earth under the previous
steining, and in these recesses the steining is carried up to the
previous work. When thus supported the intermediate portions of earth
between the sections of brickwork carried up are cut away and the
steining completed.
In sinking with a drum curb, the curb, which may be either of wood or
iron, consists of a flat ring for supporting the steining, and of a
vertical hollow cylinder or drum of the same outside diameter as the
steining, supporting the ring within it and bevelled to a sharp edge
below. The rings, or ribs, of a wooden curb are formed of two
thicknesses of elm plank, 1-1/2 inch thick by 9 inches wide, giving a
total thickness of 3 inches.
[Illustration: Iron Drum Curb Plan.
Fig. 19.]
[Illustration: Iron Curb Enlarged Segment.
Fig. 20.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account