It was provided that the canal and works were to be finished, save for
unavoidable delays, within six years. Native labour was to be employed
to the extent of four-fifths of the whole, a special convention
settling the terms on which the Government supplied or authorised such
labour. The tolls were fixed at 10 frs. per “ton of capacity” (an
expression which gave rise to difficulties subsequently), and 10 frs.
for each passenger.
A contract was made with M. Hardon for the execution of the works,
under which the company were to receive 60 per cent. of the prices
fixed by the original estimates of the International Commission. The
drawing up of the plans, the general superintendence, and the supply
of the machinery and stores, were, however, to be left in the hands of
the company. This agreement was subsequently cancelled, and the company
took the works under its own control, making contracts with four
different firms, who undertook to complete the principal undertakings
for a total sum of 4,588,800_l._[148] With these arrangements, the canal
was fairly launched. From 1861 till 1869 the whole line of the canal
was the busiest centre of industrial activity in Europe. The total
amount of excavation required was 107 millions of cubic metres. This
is a larger amount of digging than has been accomplished in the case
of any other work on record.[149] The operations were required to be
carried on at the same time with the fresh-water canal from Nefiche to
Suez, and with the maritime canal from Suez to Port Said, so that two
distinct undertakings were concurrently being constructed. Some details
as to the annual progress of the works may here be suitably introduced.
In 1861, the works were chiefly confined to digging wells along the
line of the maritime canal, to erecting sheds for 10,000 labourers, and
providing dock basins, water condensers, forges and workshops, steam
saw-mills, and opening a water supply by a canal which should join the
Nile to Lake Timsah.
In 1862, the eastern mole at Port Said was begun, together with a
landing stage 70 yards by 22, in 16 feet of water, and an arsenal dock
160 yards by 135 and 5 feet depth. Seven Arab villages were built, and
north of Lake Timsah, a sea-water cutting was continued from Kantara
to El Ferdane. A large dredging plant ordered from various makers in
England and France was delivered.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account