In 1863, four dredgers and cranes were got to work at Port Said, and
south of Lake Timsah twenty-one dredgers were at work, and three others
were nearly ready. Provision was made for adding twenty more dredgers,
each estimated to be capable of raising 1,050,000 cubic feet per month.
The fresh-water canal from Nefiche to Suez was begun, and 24 miles
were finished. This canal was 64 feet at the water-line, 26 feet at
the bottom, and had 6 feet draught of water. The excavations required
were about 50 millions of cubic feet. On the north of Lake Timsah,
18,000 men were at work, digging a trench 50 feet by 4 to 6 feet
deep, connecting the Mediterranean and Lake Timsah, and 153,600,000
cubic feet of excavation was done at 0·68 fr. per cubic metre, being
within the original estimate, despite the heavy labour of carrying the
earth up an incline of 70 feet. From Lake Timsah to Toussoum Plateau
on the south, the canal was made 190 feet wide and 6 feet below the
Mediterranean level, involving 21,200,000 cubic feet of excavation.
In 1864, 20 new dredgers, with barges and accessories, were fitted
up, 43,000,000 cubic feet of excavation was done, from Port Said to
El Ferdane, and 7,600,000 cubic feet between Timsah and Serapeum, as
well as 4,500,000 cubic feet of gypsous stone along Lake Ballah. A
large area of land was also reclaimed, in order to provide for new
works, quays were extended, and the canal Cheikh Carponti, connecting
Port Said with the lake and Damietta, was completed. The fresh-water
canal was also completed to the sea, over 55 miles, having occupied
thirteen months, and involved 118,000,000 cubic feet of excavation.
Corvées, or native forced labour, were abolished, and 7954 European
labourers, with 10,806 others, were set to work.
In 1865 the general works of the Maritime Canal were extended.
In 1866 Messrs. Borel and Levalley got 32 trough dredgers at work along
35 miles of the canal, and the canal from Port Said to Timsah was
widened to 325 feet, thus allowing of the formation of strands for the
protection of banks from passing vessels, and economising the stone
embankments. The Viceroy set 80,000 men to work at the canal from
Cairo to Wady, so as to allow of the passage of the Nile waters at all
seasons.
In 1867, 353,000,000 cubic feet of dredging was accomplished, and long
trough dredgers were applied to the work between Port Said and Timsah,
which was filled to sea level. The large lake to Chalouf, and the small
lake to Suez, were excavated by hand labour. Of the contract of M.
Couvreux to excavate 146,000,000 cubic feet, 122,500,000 cubic feet had
been completed on 1st June.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account