It would be misleading to put down any average price for tunnel-work.
So much depends upon the locality, the description of material to be
excavated, the cost of masonry or brickwork, and the cost of labour.
Added to these come the unforeseen troubles of slips and water-laden
strata, creating difficulties which baffle the miners for a time, and
add enormously to the expenditure. Some tunnels for double line have
been constructed in good ground, and under favourable circumstances as
to building materials and labour, for as low as £32 per lineal yard;
while others, carried out under adverse conditions, have cost as much
as £150 per lineal yard. A medium somewhere between the two should
represent the cost of tunnel-work through ground which does not
present any special difficulty. At the same time it must be borne in
mind that simple tunnelling which can be done in one locality for £50
or £60 per lineal yard, would be increased 20, 30, or 40 per cent. in
another, where building material for the lining is scarce and
expensive.
Tunnel-work abroad will generally cost more than the same work at
home. The native labourers may perhaps be procured at low rates, but
the skilled workmen must be brought from a distance, and will obtain
high wages.
Another form of tunnel-work, generally termed the covered-way system,
is frequently adopted in towns and places where land and space are
very valuable. This method consists in the excavating and removing of
earthwork to admit of the building of the side walls and arching of a
suitable tunnel-way, and then filling in over the top to a depth of
three or four feet, or up to the level of the original surface of the
ground. This work may be carried out by either removing the entire
width of the earthwork before the commencement of any building
operations, or by first forming two deep, well-shored trenches, in
which to build the side walls up to about arch-springing. In bad
ground the latter arrangement has the advantage, as the shoring and
strutting to hold up the sliding material is limited to the widths of
the two narrow trenches, and the centre block of earthwork is left
untouched as a support to the strutting. When the side walls have been
built sufficiently high the upper portion of the centre block of
earthwork can be removed to allow of the erection of centering and 179
building of the arching, and afterwards the remaining portion of
earthwork can be removed at convenience. In this manner a tunnel-way
may be constructed under streets, gardens, and even under buildings.
Being nearly all done in the open, the work is more under control than
in an ordinary tunnel, but it is usually very costly. Temporary or
diverted roads must be arranged; the excavated material must generally
all be removed by carts, sometimes to long distances; and provision
must be made for diverting the network of sewers, gas, and water pipes
which are intercepted along the route.