There are many kinds of rock which appear hard and compact when first
excavated, but upon exposure to the weather undergo a complete change, 227
developing into soft masses containing too much clay to allow the
water to pass through readily. Where rock is scarce and gravel
plentiful, the lower layer may be made of the heavier or coarser
gravel, leaving the finer gravel for the upper layer, or boxing; but
there is no doubt that the broken stone pitching makes the most
efficient bottom layer. No gravel ballast should be used which is not
free from clay or earthy sand.
Wherever there are particles of earthy matter, sufficient to furnish
nourishment for vegetable growth, weeds will quickly spring up, and
once established are most difficult, if not impossible, to eradicate.
The presence of weeds checks drainage, and gives an untidy appearance
to the line, besides constantly occupying a large portion of the
platelayers’ time in their removal.
Clean cinders, free from dust or earth, are much used for upper
ballast and boxing, and being lighter than gravel, are specially
applicable for soft boggy ground. Burnt clay, broken into small
pieces, has been largely adopted in districts where both rock and
gravel were difficult to obtain. Chalk, furnace-slag broken small,
crushed brick and sand, are frequently used as ballast. Sand is
objectionable where there is high-speed traffic, as the finer
particles rise in the form of dust and deposit themselves on the
vehicles and machinery of the train.
The water-tables, or side drains in the cuttings, should be cut below
the formation level, and to a depth or width sufficient to take away
all rain-water, or water arising from springs. Where the material of
the cutting is of a loose friable nature, it may be necessary to
protect the sides of the water-tables with low dry stone walls, as in
Fig. 338; or glazed earthenware pipes may be laid, as in Fig. 339,
with open joints, or with grate openings at regular intervals. In some
cases substantial side-walls and invert are requisite to carry away
the flow of water.
Timber sleepers intended for the flange railroad should have the
rail-seats grooved by machinery to ensure perfect accuracy in the
position of the grooves, and in the angle or inclination of the
rail-seats. Fig. 340 is a side view of part of a sleeper grooved to
receive a flange rail. The presence of the grooves materially
facilitate the laying of the rails to gauge, but must not be allowed
to interfere with the constant use of the platelayer’s gauge. In a
similar manner the timber sleepers for the chair road frequently have 228
the spike-holes bored to template by machinery, as indicated on Fig.
341. Steel or iron sleepers are delivered with the recesses for rails,
and holes for bolts or fastenings formed complete by machinery.