A medium-sized travelling-crane is a most useful appliance about a 297
railway station; it has a much greater range of utility than a fixed
crane, but it is not always appreciated as it should be. It merely
requires a line of rails laid down parallel to the rails of siding,
and may be placed either on the same level as the siding, or on the
level of the loading-bank. Being laid flush with the roadway, the
rails do not present any obstacle to the passage of carts or movement
of merchandise. As one waggon on the siding is loaded or unloaded, the
crane can be moved along its own line of rails, and be put to work at
another without the necessity of moving or drawing out any of the
railway waggons on the siding. Five, ten, or twenty, or more railway
waggons can be dealt with in this way, according to the length of
crane-line laid down. The crane can also be readily removed to another
part of the station-yard, or to another station along the line. For
stations with an intermittent or spasmodic traffic in heavy timber,
large blocks of stone, or other unwieldy articles, a travelling-crane
is particularly suitable, as it will meet all the wants so far as the
lifting is concerned, and when the rush of traffic is over, it can be
easily transferred to some other sphere of usefulness. The
crane-siding itself is never very costly, as the rails are generally
old rails taken out of the main line, and laid on good second-hand
sleepers. They have little to do, and merely form a track for the
moving crane.
Fig. 451 is a sketch of an ordinary Goliath crane constructed of
timber. The general arrangement and capabilities of this crane are
somewhat similar to those of the gantry shown in Fig. 447. Both of
them are designed to lift heavy weights, and move them sideways into,
or out of, ordinary road waggons, but the methods of application are
different. In the gantry the verticals are permanently fixed, whereas
in the Goliath the verticals and overhead girders are all attached and
braced together, forming a complete framework which is carried by
double flanged rollers running on the lines of rails R, R. The
winches or gearing for lifting the weights, or slinging them sideways,
or for propelling the crane forward on the rails, are attached to the
verticals as shown, and are worked from the ground-level instead of
the overhead platform, as indicated in the gantry. As each Goliath
crane is complete in itself, there is nothing to prevent two or three
of them working at the same time on a long length of crane-line.
[Illustration: Fig. 451, 452]
Fig. 452 shows an ordinary derrick crane, which, on account of the 299
large and varying sweep of the jib, is found very convenient for
certain classes of work. It occupies a considerable amount of room,
and its adoption is therefore limited to situations where space is of
secondary importance.