ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico: The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911.Conway, G. R. G. (George Robert Graham)
Science
ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico: The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911.
========================================+==============================
| FOR 1,095 PIPES 55.9 CM.
| IN DIAMETER.
Materials. +-------------+----------------
| Quantities. | Cost.
----------------------------------------+-------------+----------------
Portland cement, at 8.00 pesos per | |
bbl., delivered at pipe-making yard. | 303 bbl. | 2,424.00 pesos.
Sand, at 2.65 pesos per cu. m. | 68 cu. m.| 180.20 "
Crushed rock, 19-mm. (3/4-in.), at 2.65 | |
pesos per cu. m. | 50 cu. m.| 132.15 "
No. 6 galvanized-wire hoops. 4 rings | |
to each pipe. | 4,380 | 183.00 "
----------------------------------------+-------------+----------------
Totals. | ... | 2,919.45 pesos.
----------------------------------------+-------------+----------------
Cost per pipe. | ... | 2.66 pesos.
========================================+=============+================
_Excavation for Pipe Line and Siphons._--The excavation for the pipe
line and for bridge works, etc., was let by contract to Messrs. Scott
and Lee, of Monterrey, under three classifications:
(1) "All material which in the judgment of the Engineer can
be economically loosened with picks and handled with
shovels."
(2) "Indurated earth or gravel, shale or rock which can be
loosened without blasting, and 'sillar', locally so-called,
whether pure or mixed with other substances, and whether it
requires blasting or not."
(3) "All rock not included in the above which requires
drilling or blasting."
Locally, this classification is well understood, particularly No. 2, as
it covers the sillar soils which are common in the neighborhood of
Monterrey. The contract prices were: No. 1, 50 cents; No. 2, 1.50
pesos; and No. 3, 2.50 pesos per cu. m. These prices were over and above
the clearing and grubbing of the line, which was paid for at the rate of
100 pesos per hectare.
The route of the pipe line being along broken country, at some points
difficult of access, service roadways, about 3 m. wide, for hauling
material were constructed, and, for about 7 km., a roadway was made
along the line of the trench.
The prices for the roadway, under the above classification, were: For
No. 1, 35 cents; No. 2, 1.50 pesos; and No. 3, 2.50 pesos per cu. m.
The trenches were excavated 5 cm. below the required finishing depth, to
allow for grading the pipes in selected material, and were taken out to
an average width of 40 cm. greater than the outside diameter of the
pipe, to allow for their proper jointing, and also to give sufficient
room to roll the pipes in the trenches.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account